THE STATE OF NEW HAMPSHIRE PAGE 1 DEPARTMENT OF TRANSPORTATION PROJECT: ORFORD-PIERMONT 16476 COUNTIES AND CODES: GRAFTON 009 DATE BIDS OPEN: JUNE 6, 2012 SCOPE OF WORK: ROCK STABILIZATION LOCATION: ORFORD/PIERMONT TOWN BOUNDARY COMPLETION DATE: OCTOBER 19, 2012 A MORRILL CONSTRUCTION, INC. 190 HORSE MEADOW RD., NORTH HAVERHILL, NH 03774 $ 429,078.00 B NORTHERN CONSTRUCTION SERVICE, LLC 775 PLEASANT STREET, UNIT 11, WEYMOUTH, MA 02189 $ 797,897.00 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 203.1 COMMON EXCAVATION CY 500. 12.00 6,000.00 18.00 9,000.00 203.5554 GUARDRAIL 50' EAGRT PLATFORM U 2. 1,200.00 2,400.00 1,250.00 2,500.00 203.92 ROCK SCALING MACHINE METHOD HR 60. 500.00 30,000.00 250.00 15,000.00 224.1 HORIZONTAL DRAINS IN ROCK LF 1,000. 18.00 18,000.00 98.00 98,000.00 225.2 PRESTRESSED ROCK BOLTS LF 400. 130.00 52,000.00 260.00 104,000.00 225.3 ROCK DOWELS (UNTENSIONED ROCK BOLT) LF 400. 105.00 42,000.00 220.00 88,000.00 304.15 SAND BLANKET CY 490. 20.00 9,800.00 25.00 12,250.00 403.11 HOT BITUMINOUS PAVEMENT, MACHINE METHOD TON 225. 110.00 24,750.00 195.00 43,875.00 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON .5 250.00 125.00 250.00 125.00 417. COLD PLANING BITUMINOUS SURFACES SY 100. 50.00 5,000.00 100.00 10,000.00 604.4 RECONSTRUCTING/ADJUSTING CATCH BASIN & DROP INLET LF 2. 200.00 400.00 650.00 1,300.00 605.506 6" PERF. CORR. POLYETHYL PIPE UND. LF 200. 30.00 6,000.00 40.00 8,000.00 605.515 15" PERF. CORR. POLYETHLY PIPE UND. LF 400. 40.00 16,000.00 50.00 20,000.00 606.120 BEAM GUARDRAIL (STANDARD SECTION) (STEEL POST) LF 200. 19.00 3,800.00 22.00 4,400.00 606.1454 BEAM GUARDRAIL (TERM. UNIT TYPE EAGRT 50 FT.) U 2. 2,000.00 4,000.00 2,200.00 4,400.00 606.322 DOUBLE FACED TRANSITION RAIL, STEEL POST U 2. 1,100.00 2,200.00 1,250.00 2,500.00 606.41231 TRANSITION SINGLE SLOPE CONCRETE BARRIER, PRECAS U 2. 2,000.00 4,000.00 2,500.00 5,000.00 606.413 SINGLE SLOPE CONCRETE MEDIAN BARRIER, PRECAST LF 560. 85.00 47,600.00 138.00 77,280.00 16476 PAGE 2 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 606.95 TEMPORARY TRAFFIC CONTROL BARRIER LF 1,900. 12.00 22,800.00 20.00 38,000.00 616.1711 PORTABLE TRAFFIC SIGNAL (PTS) SYSTEM (MONTH) MON 2. 6,000.00 12,000.00 9,000.00 18,000.00 618.7 FLAGGERS HR 1,400. 25.00 35,000.00 20.00 28,000.00 619.1 MAINTENANCE OF TRAFFIC U 1. 10,000.00 10,000.00 40,000.00 40,000.00 619.253 PORTABLE CHANGEABLE MESSAGE SIGN (UNIT WEEK) UWK 6. 500.00 3,000.00 200.00 1,200.00 619.27 TRAILER-MOUNTED SPEED LIMIT SIGN U 2. 1,600.00 3,200.00 2,000.00 4,000.00 621.1 RETROREFLECTIVE MEDIAN BARRIER DELINEATOR EA 12. 9.00 108.00 7.00 84.00 632.0104 RETROREFLECTIVE PAINT PAVE. MARKING, 4" LINE LF 2,600. .40 1,040.00 1.00 2,600.00 645.3 EROSION STONE TON 300. 30.00 9,000.00 40.00 12,000.00 645.44 TEMPORARY SLOPE STABILIZATION TYPE D (WILDLIFE FRIENDLY) SY 1,335. 3.00 4,005.00 1.80 2,403.00 645.512 COMPOST SOCK FOR EROSION AND SEDIMENT CONTROL LF 600. 5.00 3,000.00 12.00 7,200.00 645.532 SILT FENCE WITH SUPPORT FENCE LF 200. 4.00 800.00 3.50 700.00 646.31 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS SY 1,000. 1.00 1,000.00 1.50 1,500.00 647.1 HUMUS CY 98. 25.00 2,450.00 60.00 5,880.00 670.104 TEMPORARY PORTABLE LIGHTING U 2. 1,300.00 2,600.00 5,000.00 10,000.00 692. MOBILIZATION U 1. 40,000.00 40,000.00 115,700.00 115,700.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 $429,078.00 $797,897.00 STATE OF NEW HAMPSHIRE DEPARTMENT OF TRANSPORTATION A-PS&E COMPARISION PROJECT: ORFORD-PIERMONT 16476 COUNTIES AND CODES: GRAFTON 009 DATE BIDS OPEN: JUNE 6, 2012 SCOPE OF WORK: ROCK STABILIZATION LOCATION: ORFORD/PIERMONT TOWN BOUNDARY COMPLETION DATE: OCTOBER 19, 2012 A MORRILL CONSTRUCTION, INC. 190 HORSE MEADOW RD., NORTH HAVERHILL, NH 03774 $ 429,078.00 B NORTHERN CONSTRUCTION SERVICE, LLC 775 PLEASANT STREET, UNIT 11, WEYMOUTH, MA 02189 $ 797,897.00 A-BIDDER PS&E ----------------------- ----------------------- A-PS&E ITEM NO. ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT DIFFERENCE 203.1 COMMON EXCAVATION CY 500. 12.00 6,000.00 20.00 10,000.00 -4,000.00 203.5554 GUARDRAIL 50' EAGRT PLATFORM U 2. 1,200.00 2,400.00 800.00 1,600.00 800.00 203.92 ROCK SCALING MACHINE METHOD HR 60. 500.00 30,000.00 275.00 16,500.00 13,500.00 224.1 HORIZONTAL DRAINS IN ROCK LF 1,000. 18.00 18,000.00 15.00 15,000.00 3,000.00 225.2 PRESTRESSED ROCK BOLTS LF 400. 130.00 52,000.00 140.00 56,000.00 -4,000.00 225.3 ROCK DOWELS (UNTENSIONED ROCK BOLT) LF 400. 105.00 42,000.00 140.00 56,000.00 -14,000.00 304.15 SAND BLANKET CY 490. 20.00 9,800.00 20.00 9,800.00 403.11 HOT BITUMINOUS PAVEMENT, MACHINE METHOD TON 225. 110.00 24,750.00 73.00 16,425.00 8,325.00 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON .5 250.00 125.00 184.00 92.00 33.00 417. COLD PLANING BITUMINOUS SURFACES SY 100. 50.00 5,000.00 8.00 800.00 4,200.00 604.4 RECONSTRUCTING/ADJUSTING CATCH BASIN & DROP INLET LF 2. 200.00 400.00 317.00 634.00 -234.00 605.506 6" PERF. CORR. POLYETHYL PIPE UND. LF 200. 30.00 6,000.00 16.00 3,200.00 2,800.00 605.515 15" PERF. CORR. POLYETHLY PIPE UND. LF 400. 40.00 16,000.00 17.00 6,800.00 9,200.00 606.120 BEAM GUARDRAIL (STANDARD SECTION) (STEEL POST) LF 200. 19.00 3,800.00 18.20 3,640.00 160.00 606.1454 BEAM GUARDRAIL (TERM. UNIT TYPE EAGRT 50 FT.) U 2. 2,000.00 4,000.00 2,205.00 4,410.00 -410.00 606.322 DOUBLE FACED TRANSITION RAIL, STEEL POST U 2. 1,100.00 2,200.00 3,500.00 7,000.00 -4,800.00 606.41231 TRANSITION SINGLE SLOPE CONCRETE BARRIER, PRECAS U 2. 2,000.00 4,000.00 1,800.00 3,600.00 400.00 16476 PAGE 2 A-BIDDER PS&E ----------------------- ----------------------- A-PS&E ITEM NO. ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT DIFFERENCE 606.413 SINGLE SLOPE CONCRETE MEDIAN BARRIER, PRECAST LF 560. 85.00 47,600.00 64.00 35,840.00 11,760.00 606.95 TEMPORARY TRAFFIC CONTROL BARRIER LF 1,900. 12.00 22,800.00 12.00 22,800.00 616.1711 PORTABLE TRAFFIC SIGNAL (PTS) SYSTEM (MONTH) MON 2. 6,000.00 12,000.00 4,500.00 9,000.00 3,000.00 618.7 FLAGGERS HR 1,400. 25.00 35,000.00 21.00 29,400.00 5,600.00 619.1 MAINTENANCE OF TRAFFIC U 1. 10,000.00 10,000.00 10,000.00 10,000.00 619.253 PORTABLE CHANGEABLE MESSAGE SIGN (UNIT WEEK) UWK 6. 500.00 3,000.00 200.00 1,200.00 1,800.00 619.27 TRAILER-MOUNTED SPEED LIMIT SIGN U 2. 1,600.00 3,200.00 1,500.00 3,000.00 200.00 621.1 RETROREFLECTIVE MEDIAN BARRIER DELINEATOR EA 12. 9.00 108.00 25.00 300.00 -192.00 632.0104 RETROREFLECTIVE PAINT PAVE. MARKING, 4" LINE LF 2,600. .40 1,040.00 .25 650.00 390.00 645.3 EROSION STONE TON 300. 30.00 9,000.00 30.00 9,000.00 645.44 TEMPORARY SLOPE STABILIZATION TYPE D (WILDLIFE FRIENDLY) SY 1,335. 3.00 4,005.00 1.80 2,403.00 1,602.00 645.512 COMPOST SOCK FOR EROSION AND SEDIMENT CONTROL LF 600. 5.00 3,000.00 5.00 3,000.00 645.532 SILT FENCE WITH SUPPORT FENCE LF 200. 4.00 800.00 4.50 900.00 -100.00 646.31 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS SY 1,000. 1.00 1,000.00 .85 850.00 150.00 647.1 HUMUS CY 98. 25.00 2,450.00 17.00 1,666.00 784.00 670.104 TEMPORARY PORTABLE LIGHTING U 2. 1,300.00 2,600.00 4,000.00 8,000.00 -5,400.00 692. MOBILIZATION U 1. 40,000.00 40,000.00 50,000.00 50,000.00 -10,000.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 $429,078.00 $404,510.00 24,568.00