THE STATE OF NEW HAMPSHIRE PAGE 1 DEPARTMENT OF TRANSPORTATION PROJECT: KEENE X-A002(310), 22272 COUNTIES AND CODES: CHESHIRE 005 DATE BIDS OPEN: MARCH 28, 2013 SCOPE OF WORK: BRIDGE REHABILITATION LOCATION: CITY OF KEENE COMPLETION DATE: OCTOBER 31, 2014 A EVROKS CORP. PO BOX 669, WINNISQUAM, NH 03289 $ 2,317,938.40 B COLD RIVER BRIDGES, LLC PO BOX 1076, WALPOLE, NH 03608 $ 2,588,116.00 C R.M. PIPER, INC. PO BOX 490, PLYMOUTH, NH 03264 $ 2,670,918.70 D THE LANE CONSTRUCTION CORPORATION 90 FIELDSTONE COURT, CHESHIRE, CT 06410 $ 2,795,738.40 E R.S. AUDLEY, INC. 609 ROUTE 3A, BOW, NH 03304 $ 2,874,116.00 F J.A. MCDONALD, INC. PO BOX 132, 585 GILMAN RD., LYNDON CENTER, VT 05850 $ 2,974,936.90 G NEW ENGLAND INFRASTRUCTURE, INC. 13 BRENT DRIVE, HUDSON, MA 01749 $ 3,021,790.00 H NORTHERN CONSTRUCTION SERVICE, LLC 775 PLEASANT STREET, UNIT 11, WEYMOUTH, MA 02189 $ 3,175,484.00 I CPM CONSTRUCTORS PO BOX B, FREEPORT, ME 04032 $ 3,257,137.00 J TBUCK CONSTRUCTION, INC. 249 MERROW RD., AUBURN, ME 04210 $ 3,260,840.00 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 202.341 REMOVAL AND HANDLING/ SEGREGATING SOLID WASTE (<1% ASBESTOS) CY 21. 1,420.00 29,820.00 300.00 6,300.00 1,550.00 32,550.00 202.7 REMOVAL OF GUARDRAIL LF 50. 2.00 100.00 25.00 1,250.00 2.10 105.00 304.301 CRUSHED GRAVEL CY 25. 60.00 1,500.00 125.00 3,125.00 40.00 1,000.00 403.11 HOT BITUMINOUS PAVEMENT, MACHINE METHOD TON 1,010. 85.00 85,850.00 105.00 106,050.00 90.00 90,900.00 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON 8. 200.00 1,600.00 300.00 2,400.00 210.00 1,680.00 403.6 PAVEMENT JOINT ADHESIVE LF 17,000. .50 8,500.00 .80 13,600.00 .42 7,140.00 403.911 HOT BITUMINOUS BRIDGE PAVEMENT, 1" BASE COURSE (F) TON 189. 150.00 28,350.00 185.00 34,965.00 160.00 30,240.00 403.99 TEMPORARY BITUMINOUS PAVEMENT TON 295. 150.00 44,250.00 125.00 36,875.00 160.00 47,200.00 417. COLD PLANING BITUMINOUS SURFACES SY 11,340. 2.00 22,680.00 3.00 34,020.00 2.10 23,814.00 22272 PAGE 2 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 502.101 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 114,000.00 114,000.00 88,000.00 88,000.00 120,000.00 120,000.00 502.102 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 103,500.00 103,500.00 150,000.00 150,000.00 110,000.00 110,000.00 502.103 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 132,000.00 132,000.00 175,000.00 175,000.00 160,000.00 160,000.00 504.101 COMMON BRIDGE EXCAVATION CY 27. 65.00 1,755.00 150.00 4,050.00 45.00 1,215.00 511.0001 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 428. 12.60 5,392.80 15.00 6,420.00 12.00 5,136.00 511.0002 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 1,230. 12.50 15,375.00 15.00 18,450.00 12.00 14,760.00 511.0003 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 1,261. 12.50 15,762.50 15.00 18,915.00 12.00 15,132.00 511.01 PREPARATION FOR CONCRETE BRIDGE DECK OVERLAY (F) SY 2,732. 10.60 28,959.20 15.00 40,980.00 10.60 28,959.20 511.02 PREPARATION FOR PARTIAL DEPTH CONCRETE BRIDGE DECK REPAIRS SY 320. 100.00 32,000.00 250.00 80,000.00 275.00 88,000.00 511.03 PREPARATION FOR FULL DEPTH CONCRETE BRIDGE DECK REPAIRS SY 160. 200.00 32,000.00 500.00 80,000.00 425.00 68,000.00 512.0201 PREPARATION FOR CONCRETE REPAIRS, CLASS II SY 20. 400.00 8,000.00 500.00 10,000.00 500.00 10,000.00 520.01 CONCRETE CLASS AA CY 37. 325.00 12,025.00 800.00 29,600.00 650.00 24,050.00 520.0201 CONCRETE CLASS AA, ABOVE FOOTINGS CY 234. 795.00 186,030.00 900.00 210,600.00 800.00 187,200.00 520.85 CONCRETE FOR BRIDGE DECK OVERLAY WITH HIGH-RANGE WATER REDUC. ADMIX. (F) CY 115. 502.00 57,730.00 800.00 92,000.00 650.00 74,750.00 534.3 WATER REPELLENT (SILANE/ SILOXANE) GAL 50. 75.00 3,750.00 75.00 3,750.00 100.00 5,000.00 538.2 BARRIER MEMBRANE, PEEL AN STICK - VERTICAL SURFACE (F) SY 41. 50.00 2,050.00 75.00 3,075.00 25.00 1,025.00 538.5 BARRIER MEMBRANE, HEAT WELDED (F) SY 420. 25.00 10,500.00 30.00 12,600.00 30.00 12,600.00 538.6 BARRIER MEMBRANE, HEAT WELDED - MACHINE METHOD (F) SY 2,862. 18.25 52,231.50 20.00 57,240.00 20.00 57,240.00 544.2 REINFORCING STEEL, EPOXY COATED (F) LB 12,500. 1.94 24,250.00 3.00 37,500.00 1.10 13,750.00 556.01 PAINTING EXISTING STRUCTURAL STEEL U 1. 272,000.00 272,000.00 275,000.00 275,000.00 300,000.00 300,000.00 556.02 PAINTING EXISTING STRUCTURAL STEEL U 1. 105,000.00 105,000.00 75,000.00 75,000.00 110,000.00 110,000.00 559.41 MODIFIED ELASTOMERIC PLUG TYPE FLEXIBLE JOINT (6" WIDE) (F) LF 170. 80.00 13,600.00 100.00 17,000.00 85.00 14,450.00 560.101 PREFABRICATED COMPRESSION SEAL EXPANSION JOINT (F) LF 50. 410.00 20,500.00 500.00 25,000.00 650.00 32,500.00 22272 PAGE 3 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 560.102 PREFABRICATED COMPRESSION SEAL EXPANSION JOINT (F) LF 79. 405.00 31,995.00 500.00 39,500.00 650.00 51,350.00 561.110 PREFABRICATED EXPANSION JOINT, TYPE A (F) LF 65. 487.00 31,655.00 500.00 32,500.00 650.00 42,250.00 562.1 SILICONE JOINT SEALANT (F LF 75. 10.00 750.00 10.00 750.00 15.00 1,125.00 563.22 BRIDGE RAIL T2 LF 510.5 94.00 47,987.00 90.00 45,945.00 95.00 48,497.50 563.223 BRIDGE RAIL T2 WITH SNOW SCREENING LF 290.2 152.00 44,110.40 130.00 37,726.00 155.00 44,981.00 563.23 BRIDGE RAIL T3 LF 118. 119.00 14,042.00 115.00 13,570.00 120.00 14,160.00 563.233 BRIDGE RAIL T3 WITH SNOW SCREENING LF 208. 143.00 29,744.00 140.00 29,120.00 150.00 31,200.00 565.222 BRIDGE APPROACH RAIL T2 (STEEL POSTS) U 6. 3,750.00 22,500.00 4,000.00 24,000.00 4,000.00 24,000.00 565.232 BRIDGE APPROACH RAIL T3 (STEEL POSTS) U 4. 4,435.00 17,740.00 4,500.00 18,000.00 4,700.00 18,800.00 570.91 RESETTING STONE MASONRY SY 25. 200.00 5,000.00 100.00 2,500.00 325.00 8,125.00 606.417 PORTABLE CONCRETE BARRIER FOR TRAFFIC CONTROL LF 1,550. 20.00 31,000.00 30.00 46,500.00 25.00 38,750.00 606.91 RESETTING OR SETTING GUARDRAIL LF 250. 10.00 2,500.00 20.00 5,000.00 10.00 2,500.00 606.9523 TEMP. IMPACT ATTENUATION DEVICE (NON-REDIRECTIVE) TEST LEVEL 3 U 4. 2,550.00 10,200.00 2,500.00 10,000.00 2,500.00 10,000.00 607.9304 RESETTING CHAIN LINK FENC WITH VINYL COATED FABRIC 4' HIGH LF 20. 25.00 500.00 40.00 800.00 25.00 500.00 615.04 TRAFFIC SIGN TYPE AA (F) SF 117. 22.00 2,574.00 40.00 4,680.00 42.00 4,914.00 615.30801 RESET BRIDGE MOUNTED TRAFFIC SIGN STRUCTURE U 3. 2,150.00 6,450.00 500.00 1,500.00 4,000.00 12,000.00 618.61 UNIFORMED OFFICERS WITH VEHICLE $ 1. 22,000.00 22,000.00 22,000.00 22,000.00 22,000.00 22,000.00 618.7 FLAGGERS HR 3,300. 10.00 33,000.00 22.50 74,250.00 23.00 75,900.00 619.1 MAINTENANCE OF TRAFFIC U 1. 67,000.00 67,000.00 10,000.00 10,000.00 95,000.00 95,000.00 619.25 PORTABLE CHANGEABLE MESSAGE SIGN U 3. 2,800.00 8,400.00 7,500.00 22,500.00 8,500.00 25,500.00 621.2 RETROREFLECTIVE BEAM GUARDRAIL DELINEATOR EA 20. 5.00 100.00 5.00 100.00 4.25 85.00 621.31 SINGLE DELINEATOR WITH POST EA 20. 35.00 700.00 40.00 800.00 50.00 1,000.00 628.2 SAWED BITUMINOUS PAVEMENT LF 775. 2.00 1,550.00 5.00 3,875.00 1.00 775.00 628.22 SAWED BITUMINOUS PAVEMENT (BRIDGE) LF 340. 2.00 680.00 5.00 1,700.00 2.00 680.00 632.0104 RETROREFLECTIVE PAINT PAVE. MARKING, 4" LINE LF 52,500. .11 5,775.00 .25 13,125.00 .12 6,300.00 632.3106 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 6" LINE LF 200. 1.50 300.00 1.00 200.00 1.60 320.00 632.3112 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 12" LINE LF 1,100. 2.00 2,200.00 2.00 2,200.00 2.10 2,310.00 632.911 OBLITERATE PAVE. MARKING LINE, 12" WIDE & UNDER LF 29,000. .30 8,700.00 .25 7,250.00 .32 9,280.00 22272 PAGE 4 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 645.531 SILT FENCE LF 850. 2.50 2,125.00 1.00 850.00 2.50 2,125.00 646.31 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS SY 100. 10.00 1,000.00 10.00 1,000.00 1.75 175.00 647.1 HUMUS CY 10. 50.00 500.00 100.00 1,000.00 12.00 120.00 670.104 TEMPORARY PORTABLE LIGHTING U 4. 7,000.00 28,000.00 7,500.00 30,000.00 4,000.00 16,000.00 670.95 TEMPORARY SAFETY FENCE LF 600. 2.50 1,500.00 4.00 2,400.00 6.00 3,600.00 692. MOBILIZATION U 1. 159,000.00 159,000.00 125,000.00 125,000.00 160,000.00 160,000.00 697.41 CRITICAL PATH METHOD (CPM) ELECTRONIC SCHEDULE U 1. 100.00 100.00 10.00 10.00 1,200.00 1,200.00 698.13 FIELD OFFICE TYPE C MON 20. 1,025.00 20,500.00 1,200.00 24,000.00 1,100.00 22,000.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 1002.1 REPAIRS OR REPLACEMENTS AS NEEDED - BRIDGE STRUCTURES $ 1. 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 1008.53 ALTERATIONS AND ADDITIONS AS NEEDED - SOLID WASTE DISPOSAL $ 1. 50,000.00 50,000.00 50,000.00 50,000.00 50,000.00 50,000.00 1010.15 FUEL ADJUSTMENT $ 1. 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 1010.2 ASPHALT CEMENT ADJUSTMENT $ 1. 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 $2,317,938.40 $2,588,116.00 $2,670,918.70 THE STATE OF NEW HAMPSHIRE PAGE 1 DEPARTMENT OF TRANSPORTATION PROJECT: KEENE X-A002(310), 22272 COUNTIES AND CODES: CHESHIRE 005 DATE BIDS OPEN: MARCH 28, 2013 SCOPE OF WORK: BRIDGE REHABILITATION LOCATION: CITY OF KEENE COMPLETION DATE: OCTOBER 31, 2014 A EVROKS CORP. PO BOX 669, WINNISQUAM, NH 03289 $ 2,317,938.40 B COLD RIVER BRIDGES, LLC PO BOX 1076, WALPOLE, NH 03608 $ 2,588,116.00 C R.M. PIPER, INC. PO BOX 490, PLYMOUTH, NH 03264 $ 2,670,918.70 D THE LANE CONSTRUCTION CORPORATION 90 FIELDSTONE COURT, CHESHIRE, CT 06410 $ 2,795,738.40 E R.S. AUDLEY, INC. 609 ROUTE 3A, BOW, NH 03304 $ 2,874,116.00 F J.A. MCDONALD, INC. PO BOX 132, 585 GILMAN RD., LYNDON CENTER, VT 05850 $ 2,974,936.90 G NEW ENGLAND INFRASTRUCTURE, INC. 13 BRENT DRIVE, HUDSON, MA 01749 $ 3,021,790.00 H NORTHERN CONSTRUCTION SERVICE, LLC 775 PLEASANT STREET, UNIT 11, WEYMOUTH, MA 02189 $ 3,175,484.00 I CPM CONSTRUCTORS PO BOX B, FREEPORT, ME 04032 $ 3,257,137.00 J TBUCK CONSTRUCTION, INC. 249 MERROW RD., AUBURN, ME 04210 $ 3,260,840.00 ------------------------------------------------------------------------------------------------------------------------------------ ITEM D E F NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 202.341 REMOVAL AND HANDLING/ SEGREGATING SOLID WASTE (<1% ASBESTOS) CY 21. 1,000.00 21,000.00 150.00 3,150.00 150.00 3,150.00 202.7 REMOVAL OF GUARDRAIL LF 50. 2.00 100.00 2.00 100.00 2.00 100.00 304.301 CRUSHED GRAVEL CY 25. 50.00 1,250.00 50.00 1,250.00 36.00 900.00 403.11 HOT BITUMINOUS PAVEMENT, MACHINE METHOD TON 1,010. 112.00 113,120.00 85.00 85,850.00 99.00 99,990.00 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON 8. 200.00 1,600.00 200.00 1,600.00 235.00 1,880.00 403.6 PAVEMENT JOINT ADHESIVE LF 17,000. .20 3,400.00 .54 9,180.00 1.00 17,000.00 403.911 HOT BITUMINOUS BRIDGE PAVEMENT, 1" BASE COURSE (F) TON 189. 260.00 49,140.00 150.00 28,350.00 235.00 44,415.00 403.99 TEMPORARY BITUMINOUS PAVEMENT TON 295. 240.00 70,800.00 185.00 54,575.00 235.00 69,325.00 417. COLD PLANING BITUMINOUS SURFACES SY 11,340. 2.20 24,948.00 2.00 22,680.00 3.75 42,525.00 22272 PAGE 2 ------------------------------------------------------------------------------------------------------------------------------------ ITEM D E F NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 502.101 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 120,000.00 120,000.00 115,000.00 115,000.00 125,000.00 125,000.00 502.102 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 140,000.00 140,000.00 85,000.00 85,000.00 115,000.00 115,000.00 502.103 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 270,000.00 270,000.00 215,000.00 215,000.00 145,000.00 145,000.00 504.101 COMMON BRIDGE EXCAVATION CY 27. 50.00 1,350.00 71.00 1,917.00 70.00 1,890.00 511.0001 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 428. 10.00 4,280.00 7.50 3,210.00 16.00 6,848.00 511.0002 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 1,230. 4.50 5,535.00 7.90 9,717.00 8.00 9,840.00 511.0003 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 1,261. 4.50 5,674.50 7.50 9,457.50 11.00 13,871.00 511.01 PREPARATION FOR CONCRETE BRIDGE DECK OVERLAY (F) SY 2,732. 45.00 122,940.00 10.00 27,320.00 7.00 19,124.00 511.02 PREPARATION FOR PARTIAL DEPTH CONCRETE BRIDGE DECK REPAIRS SY 320. 145.00 46,400.00 375.00 120,000.00 315.00 100,800.00 511.03 PREPARATION FOR FULL DEPTH CONCRETE BRIDGE DECK REPAIRS SY 160. 400.00 64,000.00 450.00 72,000.00 625.00 100,000.00 512.0201 PREPARATION FOR CONCRETE REPAIRS, CLASS II SY 20. 230.00 4,600.00 1,100.00 22,000.00 875.00 17,500.00 520.01 CONCRETE CLASS AA CY 37. 650.00 24,050.00 250.00 9,250.00 630.00 23,310.00 520.0201 CONCRETE CLASS AA, ABOVE FOOTINGS CY 234. 725.00 169,650.00 1,825.00 427,050.00 1,150.00 269,100.00 520.85 CONCRETE FOR BRIDGE DECK OVERLAY WITH HIGH-RANGE WATER REDUC. ADMIX. (F) CY 115. 500.00 57,500.00 800.00 92,000.00 700.00 80,500.00 534.3 WATER REPELLENT (SILANE/ SILOXANE) GAL 50. 75.00 3,750.00 74.00 3,700.00 75.00 3,750.00 538.2 BARRIER MEMBRANE, PEEL AN STICK - VERTICAL SURFACE (F) SY 41. 45.00 1,845.00 52.00 2,132.00 55.00 2,255.00 538.5 BARRIER MEMBRANE, HEAT WELDED (F) SY 420. 25.00 10,500.00 27.50 11,550.00 25.00 10,500.00 538.6 BARRIER MEMBRANE, HEAT WELDED - MACHINE METHOD (F) SY 2,862. 18.25 52,231.50 18.50 52,947.00 18.25 52,231.50 544.2 REINFORCING STEEL, EPOXY COATED (F) LB 12,500. 3.00 37,500.00 2.50 31,250.00 2.75 34,375.00 556.01 PAINTING EXISTING STRUCTURAL STEEL U 1. 244,000.00 244,000.00 198,500.00 198,500.00 272,000.00 272,000.00 556.02 PAINTING EXISTING STRUCTURAL STEEL U 1. 72,000.00 72,000.00 117,800.00 117,800.00 105,000.00 105,000.00 559.41 MODIFIED ELASTOMERIC PLUG TYPE FLEXIBLE JOINT (6" WIDE) (F) LF 170. 80.00 13,600.00 75.00 12,750.00 80.00 13,600.00 560.101 PREFABRICATED COMPRESSION SEAL EXPANSION JOINT (F) LF 50. 700.00 35,000.00 450.00 22,500.00 620.00 31,000.00 22272 PAGE 3 ------------------------------------------------------------------------------------------------------------------------------------ ITEM D E F NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 560.102 PREFABRICATED COMPRESSION SEAL EXPANSION JOINT (F) LF 79. 700.00 55,300.00 450.00 35,550.00 545.00 43,055.00 561.110 PREFABRICATED EXPANSION JOINT, TYPE A (F) LF 65. 700.00 45,500.00 520.00 33,800.00 510.00 33,150.00 562.1 SILICONE JOINT SEALANT (F LF 75. 25.00 1,875.00 15.00 1,125.00 55.00 4,125.00 563.22 BRIDGE RAIL T2 LF 510.5 90.00 45,945.00 98.00 50,029.00 89.00 45,434.50 563.223 BRIDGE RAIL T2 WITH SNOW SCREENING LF 290.2 147.00 42,659.40 140.00 40,628.00 147.00 42,659.40 563.23 BRIDGE RAIL T3 LF 118. 115.00 13,570.00 125.00 14,750.00 114.00 13,452.00 563.233 BRIDGE RAIL T3 WITH SNOW SCREENING LF 208. 140.00 29,120.00 150.00 31,200.00 138.00 28,704.00 565.222 BRIDGE APPROACH RAIL T2 (STEEL POSTS) U 6. 3,800.00 22,800.00 4,000.00 24,000.00 3,750.00 22,500.00 565.232 BRIDGE APPROACH RAIL T3 (STEEL POSTS) U 4. 4,450.00 17,800.00 4,400.00 17,600.00 4,435.00 17,740.00 570.91 RESETTING STONE MASONRY SY 25. 350.00 8,750.00 185.00 4,625.00 250.00 6,250.00 606.417 PORTABLE CONCRETE BARRIER FOR TRAFFIC CONTROL LF 1,550. 50.00 77,500.00 34.00 52,700.00 45.00 69,750.00 606.91 RESETTING OR SETTING GUARDRAIL LF 250. 10.00 2,500.00 10.00 2,500.00 10.00 2,500.00 606.9523 TEMP. IMPACT ATTENUATION DEVICE (NON-REDIRECTIVE) TEST LEVEL 3 U 4. 7,000.00 28,000.00 4,000.00 16,000.00 5,000.00 20,000.00 607.9304 RESETTING CHAIN LINK FENC WITH VINYL COATED FABRIC 4' HIGH LF 20. 20.00 400.00 20.00 400.00 26.00 520.00 615.04 TRAFFIC SIGN TYPE AA (F) SF 117. 40.00 4,680.00 38.00 4,446.00 40.00 4,680.00 615.30801 RESET BRIDGE MOUNTED TRAFFIC SIGN STRUCTURE U 3. 2,200.00 6,600.00 4,500.00 13,500.00 4,500.00 13,500.00 618.61 UNIFORMED OFFICERS WITH VEHICLE $ 1. 22,000.00 22,000.00 22,000.00 22,000.00 22,000.00 22,000.00 618.7 FLAGGERS HR 3,300. 20.00 66,000.00 19.00 62,700.00 22.00 72,600.00 619.1 MAINTENANCE OF TRAFFIC U 1. 55,000.00 55,000.00 25,000.00 25,000.00 145,000.00 145,000.00 619.25 PORTABLE CHANGEABLE MESSAGE SIGN U 3. 7,000.00 21,000.00 9,000.00 27,000.00 9,250.00 27,750.00 621.2 RETROREFLECTIVE BEAM GUARDRAIL DELINEATOR EA 20. 4.00 80.00 4.00 80.00 4.00 80.00 621.31 SINGLE DELINEATOR WITH POST EA 20. 100.00 2,000.00 20.00 400.00 50.00 1,000.00 628.2 SAWED BITUMINOUS PAVEMENT LF 775. 2.00 1,550.00 1.00 775.00 1.50 1,162.50 628.22 SAWED BITUMINOUS PAVEMENT (BRIDGE) LF 340. 2.00 680.00 1.00 340.00 3.00 1,020.00 632.0104 RETROREFLECTIVE PAINT PAVE. MARKING, 4" LINE LF 52,500. .11 5,775.00 .10 5,250.00 .11 5,775.00 632.3106 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 6" LINE LF 200. 1.50 300.00 2.00 400.00 1.50 300.00 632.3112 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 12" LINE LF 1,100. 2.00 2,200.00 2.20 2,420.00 2.00 2,200.00 632.911 OBLITERATE PAVE. MARKING LINE, 12" WIDE & UNDER LF 29,000. .30 8,700.00 .30 8,700.00 .30 8,700.00 22272 PAGE 4 ------------------------------------------------------------------------------------------------------------------------------------ ITEM D E F NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 645.531 SILT FENCE LF 850. 3.40 2,890.00 5.25 4,462.50 2.00 1,700.00 646.31 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS SY 100. 4.00 400.00 2.50 250.00 5.00 500.00 647.1 HUMUS CY 10. 50.00 500.00 80.00 800.00 85.00 850.00 670.104 TEMPORARY PORTABLE LIGHTING U 4. 20,000.00 80,000.00 6,000.00 24,000.00 5,500.00 22,000.00 670.95 TEMPORARY SAFETY FENCE LF 600. 4.00 2,400.00 4.00 2,400.00 2.50 1,500.00 692. MOBILIZATION U 1. 100,000.00 100,000.00 260,000.00 260,000.00 250,000.00 250,000.00 697.41 CRITICAL PATH METHOD (CPM) ELECTRONIC SCHEDULE U 1. 6,500.00 6,500.00 2,500.00 2,500.00 4,000.00 4,000.00 698.13 FIELD OFFICE TYPE C MON 20. 1,900.00 38,000.00 1,400.00 28,000.00 1,100.00 22,000.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 1002.1 REPAIRS OR REPLACEMENTS AS NEEDED - BRIDGE STRUCTURES $ 1. 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 1008.53 ALTERATIONS AND ADDITIONS AS NEEDED - SOLID WASTE DISPOSAL $ 1. 50,000.00 50,000.00 50,000.00 50,000.00 50,000.00 50,000.00 1010.15 FUEL ADJUSTMENT $ 1. 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 1010.2 ASPHALT CEMENT ADJUSTMENT $ 1. 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 $2,795,738.40 $2,874,116.00 $2,974,936.90 THE STATE OF NEW HAMPSHIRE PAGE 1 DEPARTMENT OF TRANSPORTATION PROJECT: KEENE X-A002(310), 22272 COUNTIES AND CODES: CHESHIRE 005 DATE BIDS OPEN: MARCH 28, 2013 SCOPE OF WORK: BRIDGE REHABILITATION LOCATION: CITY OF KEENE COMPLETION DATE: OCTOBER 31, 2014 A EVROKS CORP. PO BOX 669, WINNISQUAM, NH 03289 $ 2,317,938.40 B COLD RIVER BRIDGES, LLC PO BOX 1076, WALPOLE, NH 03608 $ 2,588,116.00 C R.M. PIPER, INC. PO BOX 490, PLYMOUTH, NH 03264 $ 2,670,918.70 D THE LANE CONSTRUCTION CORPORATION 90 FIELDSTONE COURT, CHESHIRE, CT 06410 $ 2,795,738.40 E R.S. AUDLEY, INC. 609 ROUTE 3A, BOW, NH 03304 $ 2,874,116.00 F J.A. MCDONALD, INC. PO BOX 132, 585 GILMAN RD., LYNDON CENTER, VT 05850 $ 2,974,936.90 G NEW ENGLAND INFRASTRUCTURE, INC. 13 BRENT DRIVE, HUDSON, MA 01749 $ 3,021,790.00 H NORTHERN CONSTRUCTION SERVICE, LLC 775 PLEASANT STREET, UNIT 11, WEYMOUTH, MA 02189 $ 3,175,484.00 I CPM CONSTRUCTORS PO BOX B, FREEPORT, ME 04032 $ 3,257,137.00 J TBUCK CONSTRUCTION, INC. 249 MERROW RD., AUBURN, ME 04210 $ 3,260,840.00 ------------------------------------------------------------------------------------------------------------------------------------ ITEM G H I NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 202.341 REMOVAL AND HANDLING/ SEGREGATING SOLID WASTE (<1% ASBESTOS) CY 21. 1,200.00 25,200.00 500.00 10,500.00 500.00 10,500.00 202.7 REMOVAL OF GUARDRAIL LF 50. 3.00 150.00 5.00 250.00 2.40 120.00 304.301 CRUSHED GRAVEL CY 25. 90.00 2,250.00 35.00 875.00 100.00 2,500.00 403.11 HOT BITUMINOUS PAVEMENT, MACHINE METHOD TON 1,010. 115.00 116,150.00 100.00 101,000.00 98.90 99,889.00 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON 8. 270.00 2,160.00 150.00 1,200.00 250.00 2,000.00 403.6 PAVEMENT JOINT ADHESIVE LF 17,000. .30 5,100.00 .30 5,100.00 .90 15,300.00 403.911 HOT BITUMINOUS BRIDGE PAVEMENT, 1" BASE COURSE (F) TON 189. 270.00 51,030.00 100.00 18,900.00 235.00 44,415.00 403.99 TEMPORARY BITUMINOUS PAVEMENT TON 295. 270.00 79,650.00 130.00 38,350.00 235.00 69,325.00 417. COLD PLANING BITUMINOUS SURFACES SY 11,340. 5.00 56,700.00 4.00 45,360.00 4.50 51,030.00 22272 PAGE 2 ------------------------------------------------------------------------------------------------------------------------------------ ITEM G H I NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 502.101 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 75,000.00 75,000.00 165,000.00 165,000.00 120,000.00 120,000.00 502.102 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 60,000.00 60,000.00 160,000.00 160,000.00 110,000.00 110,000.00 502.103 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 185,000.00 185,000.00 230,000.00 230,000.00 200,000.00 200,000.00 504.101 COMMON BRIDGE EXCAVATION CY 27. 100.00 2,700.00 40.00 1,080.00 100.00 2,700.00 511.0001 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 428. 7.00 2,996.00 15.00 6,420.00 15.00 6,420.00 511.0002 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 1,230. 7.00 8,610.00 15.00 18,450.00 13.50 16,605.00 511.0003 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 1,261. 7.00 8,827.00 15.00 18,915.00 14.00 17,654.00 511.01 PREPARATION FOR CONCRETE BRIDGE DECK OVERLAY (F) SY 2,732. 8.00 21,856.00 12.00 32,784.00 10.00 27,320.00 511.02 PREPARATION FOR PARTIAL DEPTH CONCRETE BRIDGE DECK REPAIRS SY 320. 150.00 48,000.00 200.00 64,000.00 500.00 160,000.00 511.03 PREPARATION FOR FULL DEPTH CONCRETE BRIDGE DECK REPAIRS SY 160. 350.00 56,000.00 500.00 80,000.00 800.00 128,000.00 512.0201 PREPARATION FOR CONCRETE REPAIRS, CLASS II SY 20. 450.00 9,000.00 800.00 16,000.00 800.00 16,000.00 520.01 CONCRETE CLASS AA CY 37. 300.00 11,100.00 600.00 22,200.00 480.00 17,760.00 520.0201 CONCRETE CLASS AA, ABOVE FOOTINGS CY 234. 1,000.00 234,000.00 1,000.00 234,000.00 1,500.00 351,000.00 520.85 CONCRETE FOR BRIDGE DECK OVERLAY WITH HIGH-RANGE WATER REDUC. ADMIX. (F) CY 115. 1,300.00 149,500.00 1,050.00 120,750.00 580.00 66,700.00 534.3 WATER REPELLENT (SILANE/ SILOXANE) GAL 50. 30.00 1,500.00 225.00 11,250.00 100.00 5,000.00 538.2 BARRIER MEMBRANE, PEEL AN STICK - VERTICAL SURFACE (F) SY 41. 70.00 2,870.00 35.00 1,435.00 71.00 2,911.00 538.5 BARRIER MEMBRANE, HEAT WELDED (F) SY 420. 30.00 12,600.00 25.00 10,500.00 26.00 10,920.00 538.6 BARRIER MEMBRANE, HEAT WELDED - MACHINE METHOD (F) SY 2,862. 22.00 62,964.00 20.00 57,240.00 25.00 71,550.00 544.2 REINFORCING STEEL, EPOXY COATED (F) LB 12,500. 1.50 18,750.00 2.00 25,000.00 3.50 43,750.00 556.01 PAINTING EXISTING STRUCTURAL STEEL U 1. 230,000.00 230,000.00 375,000.00 375,000.00 350,000.00 350,000.00 556.02 PAINTING EXISTING STRUCTURAL STEEL U 1. 140,000.00 140,000.00 215,000.00 215,000.00 120,000.00 120,000.00 559.41 MODIFIED ELASTOMERIC PLUG TYPE FLEXIBLE JOINT (6" WIDE) (F) LF 170. 90.00 15,300.00 80.00 13,600.00 110.00 18,700.00 560.101 PREFABRICATED COMPRESSION SEAL EXPANSION JOINT (F) LF 50. 550.00 27,500.00 600.00 30,000.00 610.00 30,500.00 22272 PAGE 3 ------------------------------------------------------------------------------------------------------------------------------------ ITEM G H I NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 560.102 PREFABRICATED COMPRESSION SEAL EXPANSION JOINT (F) LF 79. 550.00 43,450.00 600.00 47,400.00 510.00 40,290.00 561.110 PREFABRICATED EXPANSION JOINT, TYPE A (F) LF 65. 600.00 39,000.00 600.00 39,000.00 600.00 39,000.00 562.1 SILICONE JOINT SEALANT (F LF 75. 3.00 225.00 5.00 375.00 6.00 450.00 563.22 BRIDGE RAIL T2 LF 510.5 100.00 51,050.00 130.00 66,365.00 100.00 51,050.00 563.223 BRIDGE RAIL T2 WITH SNOW SCREENING LF 290.2 160.00 46,432.00 250.00 72,550.00 150.00 43,530.00 563.23 BRIDGE RAIL T3 LF 118. 125.00 14,750.00 130.00 15,340.00 130.00 15,340.00 563.233 BRIDGE RAIL T3 WITH SNOW SCREENING LF 208. 150.00 31,200.00 225.00 46,800.00 160.00 33,280.00 565.222 BRIDGE APPROACH RAIL T2 (STEEL POSTS) U 6. 4,000.00 24,000.00 4,500.00 27,000.00 4,500.00 27,000.00 565.232 BRIDGE APPROACH RAIL T3 (STEEL POSTS) U 4. 5,000.00 20,000.00 4,500.00 18,000.00 5,400.00 21,600.00 570.91 RESETTING STONE MASONRY SY 25. 500.00 12,500.00 150.00 3,750.00 360.00 9,000.00 606.417 PORTABLE CONCRETE BARRIER FOR TRAFFIC CONTROL LF 1,550. 50.00 77,500.00 35.00 54,250.00 32.00 49,600.00 606.91 RESETTING OR SETTING GUARDRAIL LF 250. 11.00 2,750.00 15.00 3,750.00 12.00 3,000.00 606.9523 TEMP. IMPACT ATTENUATION DEVICE (NON-REDIRECTIVE) TEST LEVEL 3 U 4. 6,000.00 24,000.00 5,000.00 20,000.00 3,000.00 12,000.00 607.9304 RESETTING CHAIN LINK FENC WITH VINYL COATED FABRIC 4' HIGH LF 20. 12.00 240.00 20.00 400.00 20.00 400.00 615.04 TRAFFIC SIGN TYPE AA (F) SF 117. 50.00 5,850.00 20.00 2,340.00 48.00 5,616.00 615.30801 RESET BRIDGE MOUNTED TRAFFIC SIGN STRUCTURE U 3. 2,000.00 6,000.00 5,000.00 15,000.00 6,500.00 19,500.00 618.61 UNIFORMED OFFICERS WITH VEHICLE $ 1. 22,000.00 22,000.00 22,000.00 22,000.00 22,000.00 22,000.00 618.7 FLAGGERS HR 3,300. 25.00 82,500.00 20.00 66,000.00 24.00 79,200.00 619.1 MAINTENANCE OF TRAFFIC U 1. 100,000.00 100,000.00 75,000.00 75,000.00 23,000.00 23,000.00 619.25 PORTABLE CHANGEABLE MESSAGE SIGN U 3. 25,000.00 75,000.00 5,000.00 15,000.00 17,000.00 51,000.00 621.2 RETROREFLECTIVE BEAM GUARDRAIL DELINEATOR EA 20. 5.00 100.00 5.00 100.00 5.00 100.00 621.31 SINGLE DELINEATOR WITH POST EA 20. 60.00 1,200.00 35.00 700.00 60.00 1,200.00 628.2 SAWED BITUMINOUS PAVEMENT LF 775. 2.00 1,550.00 2.00 1,550.00 1.20 930.00 628.22 SAWED BITUMINOUS PAVEMENT (BRIDGE) LF 340. 2.00 680.00 2.00 680.00 3.30 1,122.00 632.0104 RETROREFLECTIVE PAINT PAVE. MARKING, 4" LINE LF 52,500. .10 5,250.00 .25 13,125.00 .12 6,300.00 632.3106 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 6" LINE LF 200. 2.00 400.00 1.00 200.00 1.80 360.00 632.3112 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 12" LINE LF 1,100. 2.50 2,750.00 2.00 2,200.00 2.40 2,640.00 632.911 OBLITERATE PAVE. MARKING LINE, 12" WIDE & UNDER LF 29,000. .40 11,600.00 .75 21,750.00 .35 10,150.00 22272 PAGE 4 ------------------------------------------------------------------------------------------------------------------------------------ ITEM G H I NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 645.531 SILT FENCE LF 850. 9.00 7,650.00 4.00 3,400.00 2.20 1,870.00 646.31 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS SY 100. 12.00 1,200.00 2.00 200.00 2.40 240.00 647.1 HUMUS CY 10. 50.00 500.00 30.00 300.00 70.00 700.00 670.104 TEMPORARY PORTABLE LIGHTING U 4. 7,000.00 28,000.00 7,500.00 30,000.00 8,000.00 32,000.00 670.95 TEMPORARY SAFETY FENCE LF 600. 10.00 6,000.00 8.00 4,800.00 3.50 2,100.00 692. MOBILIZATION U 1. 300,000.00 300,000.00 125,000.00 125,000.00 250,000.00 250,000.00 697.41 CRITICAL PATH METHOD (CPM) ELECTRONIC SCHEDULE U 1. 25,000.00 25,000.00 10,000.00 10,000.00 4,000.00 4,000.00 698.13 FIELD OFFICE TYPE C MON 20. 2,200.00 44,000.00 1,800.00 36,000.00 1,200.00 24,000.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 1002.1 REPAIRS OR REPLACEMENTS AS NEEDED - BRIDGE STRUCTURES $ 1. 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 1008.53 ALTERATIONS AND ADDITIONS AS NEEDED - SOLID WASTE DISPOSAL $ 1. 50,000.00 50,000.00 50,000.00 50,000.00 50,000.00 50,000.00 1010.15 FUEL ADJUSTMENT $ 1. 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 1010.2 ASPHALT CEMENT ADJUSTMENT $ 1. 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 $3,021,790.00 $3,175,484.00 $3,257,137.00 THE STATE OF NEW HAMPSHIRE PAGE 1 DEPARTMENT OF TRANSPORTATION PROJECT: KEENE X-A002(310), 22272 COUNTIES AND CODES: CHESHIRE 005 DATE BIDS OPEN: MARCH 28, 2013 SCOPE OF WORK: BRIDGE REHABILITATION LOCATION: CITY OF KEENE COMPLETION DATE: OCTOBER 31, 2014 A EVROKS CORP. PO BOX 669, WINNISQUAM, NH 03289 $ 2,317,938.40 B COLD RIVER BRIDGES, LLC PO BOX 1076, WALPOLE, NH 03608 $ 2,588,116.00 C R.M. PIPER, INC. PO BOX 490, PLYMOUTH, NH 03264 $ 2,670,918.70 D THE LANE CONSTRUCTION CORPORATION 90 FIELDSTONE COURT, CHESHIRE, CT 06410 $ 2,795,738.40 E R.S. AUDLEY, INC. 609 ROUTE 3A, BOW, NH 03304 $ 2,874,116.00 F J.A. MCDONALD, INC. PO BOX 132, 585 GILMAN RD., LYNDON CENTER, VT 05850 $ 2,974,936.90 G NEW ENGLAND INFRASTRUCTURE, INC. 13 BRENT DRIVE, HUDSON, MA 01749 $ 3,021,790.00 H NORTHERN CONSTRUCTION SERVICE, LLC 775 PLEASANT STREET, UNIT 11, WEYMOUTH, MA 02189 $ 3,175,484.00 I CPM CONSTRUCTORS PO BOX B, FREEPORT, ME 04032 $ 3,257,137.00 J TBUCK CONSTRUCTION, INC. 249 MERROW RD., AUBURN, ME 04210 $ 3,260,840.00 ------------------------------------------------------------------------------------------------------------------------------------ ITEM J NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 202.341 REMOVAL AND HANDLING/ SEGREGATING SOLID WASTE (<1% ASBESTOS) CY 21. 1,900.00 39,900.00 202.7 REMOVAL OF GUARDRAIL LF 50. 2.00 100.00 304.301 CRUSHED GRAVEL CY 25. 50.00 1,250.00 403.11 HOT BITUMINOUS PAVEMENT, MACHINE METHOD TON 1,010. 85.00 85,850.00 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON 8. 220.00 1,760.00 403.6 PAVEMENT JOINT ADHESIVE LF 17,000. .25 4,250.00 403.911 HOT BITUMINOUS BRIDGE PAVEMENT, 1" BASE COURSE (F) TON 189. 220.00 41,580.00 403.99 TEMPORARY BITUMINOUS PAVEMENT TON 295. 220.00 64,900.00 417. COLD PLANING BITUMINOUS SURFACES SY 11,340. 6.00 68,040.00 22272 PAGE 2 ------------------------------------------------------------------------------------------------------------------------------------ ITEM J NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 502.101 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 100,000.00 100,000.00 502.102 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 100,000.00 100,000.00 502.103 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 125,000.00 125,000.00 504.101 COMMON BRIDGE EXCAVATION CY 27. 40.00 1,080.00 511.0001 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 428. 17.00 7,276.00 511.0002 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 1,230. 15.00 18,450.00 511.0003 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 1,261. 15.00 18,915.00 511.01 PREPARATION FOR CONCRETE BRIDGE DECK OVERLAY (F) SY 2,732. 8.00 21,856.00 511.02 PREPARATION FOR PARTIAL DEPTH CONCRETE BRIDGE DECK REPAIRS SY 320. 275.00 88,000.00 511.03 PREPARATION FOR FULL DEPTH CONCRETE BRIDGE DECK REPAIRS SY 160. 465.00 74,400.00 512.0201 PREPARATION FOR CONCRETE REPAIRS, CLASS II SY 20. 750.00 15,000.00 520.01 CONCRETE CLASS AA CY 37. 950.00 35,150.00 520.0201 CONCRETE CLASS AA, ABOVE FOOTINGS CY 234. 1,250.00 292,500.00 520.85 CONCRETE FOR BRIDGE DECK OVERLAY WITH HIGH-RANGE WATER REDUC. ADMIX. (F) CY 115. 725.00 83,375.00 534.3 WATER REPELLENT (SILANE/ SILOXANE) GAL 50. 50.00 2,500.00 538.2 BARRIER MEMBRANE, PEEL AN STICK - VERTICAL SURFACE (F) SY 41. 50.00 2,050.00 538.5 BARRIER MEMBRANE, HEAT WELDED (F) SY 420. 25.00 10,500.00 538.6 BARRIER MEMBRANE, HEAT WELDED - MACHINE METHOD (F) SY 2,862. 18.25 52,231.50 544.2 REINFORCING STEEL, EPOXY COATED (F) LB 12,500. 1.50 18,750.00 556.01 PAINTING EXISTING STRUCTURAL STEEL U 1. 400,000.00 400,000.00 556.02 PAINTING EXISTING STRUCTURAL STEEL U 1. 314,426.60 314,426.60 559.41 MODIFIED ELASTOMERIC PLUG TYPE FLEXIBLE JOINT (6" WIDE) (F) LF 170. 80.00 13,600.00 560.101 PREFABRICATED COMPRESSION SEAL EXPANSION JOINT (F) LF 50. 550.00 27,500.00 22272 PAGE 3 ------------------------------------------------------------------------------------------------------------------------------------ ITEM J NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 560.102 PREFABRICATED COMPRESSION SEAL EXPANSION JOINT (F) LF 79. 500.00 39,500.00 561.110 PREFABRICATED EXPANSION JOINT, TYPE A (F) LF 65. 530.00 34,450.00 562.1 SILICONE JOINT SEALANT (F LF 75. 25.00 1,875.00 563.22 BRIDGE RAIL T2 LF 510.5 89.00 45,434.50 563.223 BRIDGE RAIL T2 WITH SNOW SCREENING LF 290.2 147.00 42,659.40 563.23 BRIDGE RAIL T3 LF 118. 114.00 13,452.00 563.233 BRIDGE RAIL T3 WITH SNOW SCREENING LF 208. 138.00 28,704.00 565.222 BRIDGE APPROACH RAIL T2 (STEEL POSTS) U 6. 3,750.00 22,500.00 565.232 BRIDGE APPROACH RAIL T3 (STEEL POSTS) U 4. 4,500.00 18,000.00 570.91 RESETTING STONE MASONRY SY 25. 125.00 3,125.00 606.417 PORTABLE CONCRETE BARRIER FOR TRAFFIC CONTROL LF 1,550. 56.00 86,800.00 606.91 RESETTING OR SETTING GUARDRAIL LF 250. 10.00 2,500.00 606.9523 TEMP. IMPACT ATTENUATION DEVICE (NON-REDIRECTIVE) TEST LEVEL 3 U 4. 5,000.00 20,000.00 607.9304 RESETTING CHAIN LINK FENC WITH VINYL COATED FABRIC 4' HIGH LF 20. 20.00 400.00 615.04 TRAFFIC SIGN TYPE AA (F) SF 117. 40.00 4,680.00 615.30801 RESET BRIDGE MOUNTED TRAFFIC SIGN STRUCTURE U 3. 3,600.00 10,800.00 618.61 UNIFORMED OFFICERS WITH VEHICLE $ 1. 22,000.00 22,000.00 618.7 FLAGGERS HR 3,300. 20.00 66,000.00 619.1 MAINTENANCE OF TRAFFIC U 1. 32,000.00 32,000.00 619.25 PORTABLE CHANGEABLE MESSAGE SIGN U 3. 10,000.00 30,000.00 621.2 RETROREFLECTIVE BEAM GUARDRAIL DELINEATOR EA 20. 4.00 80.00 621.31 SINGLE DELINEATOR WITH POST EA 20. 4.00 80.00 628.2 SAWED BITUMINOUS PAVEMENT LF 775. 5.00 3,875.00 628.22 SAWED BITUMINOUS PAVEMENT (BRIDGE) LF 340. 4.00 1,360.00 632.0104 RETROREFLECTIVE PAINT PAVE. MARKING, 4" LINE LF 52,500. .11 5,775.00 632.3106 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 6" LINE LF 200. 1.50 300.00 632.3112 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 12" LINE LF 1,100. 2.00 2,200.00 632.911 OBLITERATE PAVE. MARKING LINE, 12" WIDE & UNDER LF 29,000. .30 8,700.00 22272 PAGE 4 ------------------------------------------------------------------------------------------------------------------------------------ ITEM J NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 645.531 SILT FENCE LF 850. 4.00 3,400.00 646.31 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS SY 100. 5.00 500.00 647.1 HUMUS CY 10. 50.00 500.00 670.104 TEMPORARY PORTABLE LIGHTING U 4. 3,500.00 14,000.00 670.95 TEMPORARY SAFETY FENCE LF 600. 25.00 15,000.00 692. MOBILIZATION U 1. 340,000.00 340,000.00 697.41 CRITICAL PATH METHOD (CPM) ELECTRONIC SCHEDULE U 1. 1,000.00 1,000.00 698.13 FIELD OFFICE TYPE C MON 20. 1,200.00 24,000.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 5,000.00 5,000.00 1002.1 REPAIRS OR REPLACEMENTS AS NEEDED - BRIDGE STRUCTURES $ 1. 100,000.00 100,000.00 1008.53 ALTERATIONS AND ADDITIONS AS NEEDED - SOLID WASTE DISPOSAL $ 1. 50,000.00 50,000.00 1010.15 FUEL ADJUSTMENT $ 1. 20,000.00 20,000.00 1010.2 ASPHALT CEMENT ADJUSTMENT $ 1. 10,000.00 10,000.00 $3,260,840.00 STATE OF NEW HAMPSHIRE DEPARTMENT OF TRANSPORTATION A-PS&E COMPARISION PROJECT: KEENE X-A002(310), 22272 COUNTIES AND CODES: CHESHIRE 005 DATE BIDS OPEN: MARCH 28, 2013 SCOPE OF WORK: BRIDGE REHABILITATION LOCATION: CITY OF KEENE COMPLETION DATE: OCTOBER 31, 2014 A EVROKS CORP. PO BOX 669, WINNISQUAM, NH 03289 $ 2,317,938.40 B COLD RIVER BRIDGES, LLC PO BOX 1076, WALPOLE, NH 03608 $ 2,588,116.00 C R.M. PIPER, INC. PO BOX 490, PLYMOUTH, NH 03264 $ 2,670,918.70 D THE LANE CONSTRUCTION CORPORATION 90 FIELDSTONE COURT, CHESHIRE, CT 06410 $ 2,795,738.40 E R.S. AUDLEY, INC. 609 ROUTE 3A, BOW, NH 03304 $ 2,874,116.00 F J.A. MCDONALD, INC. PO BOX 132, 585 GILMAN RD., LYNDON CENTER, VT 05850 $ 2,974,936.90 G NEW ENGLAND INFRASTRUCTURE, INC. 13 BRENT DRIVE, HUDSON, MA 01749 $ 3,021,790.00 H NORTHERN CONSTRUCTION SERVICE, LLC 775 PLEASANT STREET, UNIT 11, WEYMOUTH, MA 02189 $ 3,175,484.00 I CPM CONSTRUCTORS PO BOX B, FREEPORT, ME 04032 $ 3,257,137.00 J TBUCK CONSTRUCTION, INC. 249 MERROW RD., AUBURN, ME 04210 $ 3,260,840.00 A-BIDDER PS&E ----------------------- ----------------------- A-PS&E ITEM NO. ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT DIFFERENCE 202.341 REMOVAL AND HANDLING/ SEGREGATING SOLID WASTE (<1% ASBESTOS) CY 21. 1,420.00 29,820.00 300.00 6,300.00 23,520.00 202.7 REMOVAL OF GUARDRAIL LF 50. 2.00 100.00 3.00 150.00 -50.00 304.301 CRUSHED GRAVEL CY 25. 60.00 1,500.00 25.00 625.00 875.00 403.11 HOT BITUMINOUS PAVEMENT, MACHINE METHOD TON 1,010. 85.00 85,850.00 75.00 75,750.00 10,100.00 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON 8. 200.00 1,600.00 125.00 1,000.00 600.00 403.6 PAVEMENT JOINT ADHESIVE LF 17,000. .50 8,500.00 .30 5,100.00 3,400.00 403.911 HOT BITUMINOUS BRIDGE PAVEMENT, 1" BASE COURSE (F) TON 189. 150.00 28,350.00 150.00 28,350.00 403.99 TEMPORARY BITUMINOUS PAVEMENT TON 295. 150.00 44,250.00 70.00 20,650.00 23,600.00 22272 PAGE 2 A-BIDDER PS&E ----------------------- ----------------------- A-PS&E ITEM NO. ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT DIFFERENCE 417. COLD PLANING BITUMINOUS SURFACES SY 11,340. 2.00 22,680.00 2.50 28,350.00 -5,670.00 502.101 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 114,000.00 114,000.00 75,000.00 75,000.00 39,000.00 502.102 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 103,500.00 103,500.00 100,000.00 100,000.00 3,500.00 502.103 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 132,000.00 132,000.00 150,000.00 150,000.00 -18,000.00 504.101 COMMON BRIDGE EXCAVATION CY 27. 65.00 1,755.00 10.00 270.00 1,485.00 511.0001 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 428. 12.60 5,392.80 15.00 6,420.00 -1,027.20 511.0002 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 1,230. 12.50 15,375.00 15.00 18,450.00 -3,075.00 511.0003 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 1,261. 12.50 15,762.50 15.00 18,915.00 -3,152.50 511.01 PREPARATION FOR CONCRETE BRIDGE DECK OVERLAY (F) SY 2,732. 10.60 28,959.20 100.00 273,200.00 -244,240.80 511.02 PREPARATION FOR PARTIAL DEPTH CONCRETE BRIDGE DECK REPAIRS SY 320. 100.00 32,000.00 300.00 96,000.00 -64,000.00 511.03 PREPARATION FOR FULL DEPTH CONCRETE BRIDGE DECK REPAIRS SY 160. 200.00 32,000.00 550.00 88,000.00 -56,000.00 512.0201 PREPARATION FOR CONCRETE REPAIRS, CLASS II SY 20. 400.00 8,000.00 600.00 12,000.00 -4,000.00 520.01 CONCRETE CLASS AA CY 37. 325.00 12,025.00 850.00 31,450.00 -19,425.00 520.0201 CONCRETE CLASS AA, ABOVE FOOTINGS CY 234. 795.00 186,030.00 1,000.00 234,000.00 -47,970.00 520.85 CONCRETE FOR BRIDGE DECK OVERLAY WITH HIGH-RANGE WATER REDUC. ADMIX. (F) CY 115. 502.00 57,730.00 1,000.00 115,000.00 -57,270.00 534.3 WATER REPELLENT (SILANE/ SILOXANE) GAL 50. 75.00 3,750.00 80.00 4,000.00 -250.00 538.2 BARRIER MEMBRANE, PEEL AN STICK - VERTICAL SURFACE (F) SY 41. 50.00 2,050.00 50.00 2,050.00 538.5 BARRIER MEMBRANE, HEAT WELDED (F) SY 420. 25.00 10,500.00 25.00 10,500.00 538.6 BARRIER MEMBRANE, HEAT WELDED - MACHINE METHOD (F) SY 2,862. 18.25 52,231.50 25.00 71,550.00 -19,318.50 544.2 REINFORCING STEEL, EPOXY COATED (F) LB 12,500. 1.94 24,250.00 1.50 18,750.00 5,500.00 556.01 PAINTING EXISTING STRUCTURAL STEEL U 1. 272,000.00 272,000.00 200,000.00 200,000.00 72,000.00 556.02 PAINTING EXISTING STRUCTURAL STEEL U 1. 105,000.00 105,000.00 100,000.00 100,000.00 5,000.00 559.41 MODIFIED ELASTOMERIC PLUG TYPE FLEXIBLE JOINT (6" WIDE) (F) LF 170. 80.00 13,600.00 80.00 13,600.00 560.101 PREFABRICATED COMPRESSION SEAL EXPANSION JOINT (F) LF 50. 410.00 20,500.00 500.00 25,000.00 -4,500.00 22272 PAGE 3 A-BIDDER PS&E ----------------------- ----------------------- A-PS&E ITEM NO. ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT DIFFERENCE 560.102 PREFABRICATED COMPRESSION SEAL EXPANSION JOINT (F) LF 79. 405.00 31,995.00 500.00 39,500.00 -7,505.00 561.110 PREFABRICATED EXPANSION JOINT, TYPE A (F) LF 65. 487.00 31,655.00 550.00 35,750.00 -4,095.00 562.1 SILICONE JOINT SEALANT (F LF 75. 10.00 750.00 15.00 1,125.00 -375.00 563.22 BRIDGE RAIL T2 LF 510.5 94.00 47,987.00 110.00 56,155.00 -8,168.00 563.223 BRIDGE RAIL T2 WITH SNOW SCREENING LF 290.2 152.00 44,110.40 150.00 43,530.00 580.40 563.23 BRIDGE RAIL T3 LF 118. 119.00 14,042.00 130.00 15,340.00 -1,298.00 563.233 BRIDGE RAIL T3 WITH SNOW SCREENING LF 208. 143.00 29,744.00 170.00 35,360.00 -5,616.00 565.222 BRIDGE APPROACH RAIL T2 (STEEL POSTS) U 6. 3,750.00 22,500.00 250.00 1,500.00 21,000.00 565.232 BRIDGE APPROACH RAIL T3 (STEEL POSTS) U 4. 4,435.00 17,740.00 1,200.00 4,800.00 12,940.00 570.91 RESETTING STONE MASONRY SY 25. 200.00 5,000.00 600.00 15,000.00 -10,000.00 606.417 PORTABLE CONCRETE BARRIER FOR TRAFFIC CONTROL LF 1,550. 20.00 31,000.00 20.00 31,000.00 606.91 RESETTING OR SETTING GUARDRAIL LF 250. 10.00 2,500.00 12.00 3,000.00 -500.00 606.9523 TEMP. IMPACT ATTENUATION DEVICE (NON-REDIRECTIVE) TEST LEVEL 3 U 4. 2,550.00 10,200.00 5,000.00 20,000.00 -9,800.00 607.9304 RESETTING CHAIN LINK FENC WITH VINYL COATED FABRIC 4' HIGH LF 20. 25.00 500.00 20.00 400.00 100.00 615.04 TRAFFIC SIGN TYPE AA (F) SF 117. 22.00 2,574.00 25.00 2,925.00 -351.00 615.30801 RESET BRIDGE MOUNTED TRAFFIC SIGN STRUCTURE U 3. 2,150.00 6,450.00 2,250.00 6,750.00 -300.00 618.61 UNIFORMED OFFICERS WITH VEHICLE $ 1. 22,000.00 22,000.00 22,000.00 22,000.00 618.7 FLAGGERS HR 3,300. 10.00 33,000.00 20.00 66,000.00 -33,000.00 619.1 MAINTENANCE OF TRAFFIC U 1. 67,000.00 67,000.00 20,000.00 20,000.00 47,000.00 619.25 PORTABLE CHANGEABLE MESSAGE SIGN U 3. 2,800.00 8,400.00 7,000.00 21,000.00 -12,600.00 621.2 RETROREFLECTIVE BEAM GUARDRAIL DELINEATOR EA 20. 5.00 100.00 5.00 100.00 621.31 SINGLE DELINEATOR WITH POST EA 20. 35.00 700.00 30.00 600.00 100.00 628.2 SAWED BITUMINOUS PAVEMENT LF 775. 2.00 1,550.00 1.25 968.75 581.25 628.22 SAWED BITUMINOUS PAVEMENT (BRIDGE) LF 340. 2.00 680.00 5.00 1,700.00 -1,020.00 632.0104 RETROREFLECTIVE PAINT PAVE. MARKING, 4" LINE LF 52,500. .11 5,775.00 .15 7,875.00 -2,100.00 632.3106 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 6" LINE LF 200. 1.50 300.00 1.00 200.00 100.00 632.3112 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 12" LINE LF 1,100. 2.00 2,200.00 2.00 2,200.00 632.911 OBLITERATE PAVE. MARKING LINE, 12" WIDE & UNDER LF 29,000. .30 8,700.00 .30 8,700.00 645.531 SILT FENCE LF 850. 2.50 2,125.00 2.50 2,125.00 646.31 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS SY 100. 10.00 1,000.00 .50 50.00 950.00 22272 PAGE 4 A-BIDDER PS&E ----------------------- ----------------------- A-PS&E ITEM NO. ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT DIFFERENCE 647.1 HUMUS CY 10. 50.00 500.00 16.00 160.00 340.00 670.104 TEMPORARY PORTABLE LIGHTING U 4. 7,000.00 28,000.00 6,000.00 24,000.00 4,000.00 670.95 TEMPORARY SAFETY FENCE LF 600. 2.50 1,500.00 4.00 2,400.00 -900.00 692. MOBILIZATION U 1. 159,000.00 159,000.00 250,000.00 250,000.00 -91,000.00 697.41 CRITICAL PATH METHOD (CPM) ELECTRONIC SCHEDULE U 1. 100.00 100.00 2,000.00 2,000.00 -1,900.00 698.13 FIELD OFFICE TYPE C MON 20. 1,025.00 20,500.00 1,500.00 30,000.00 -9,500.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 1002.1 REPAIRS OR REPLACEMENTS AS NEEDED - BRIDGE STRUCTURES $ 1. 100,000.00 100,000.00 100,000.00 100,000.00 1008.53 ALTERATIONS AND ADDITIONS AS NEEDED - SOLID WASTE DISPOSAL $ 1. 50,000.00 50,000.00 50,000.00 50,000.00 1010.15 FUEL ADJUSTMENT $ 1. 20,000.00 20,000.00 20,000.00 20,000.00 1010.2 ASPHALT CEMENT ADJUSTMENT $ 1. 10,000.00 10,000.00 10,000.00 10,000.00 $2,317,938.40 $2,789,643.75 -471,705.35