THE STATE OF NEW HAMPSHIRE PAGE 1 DEPARTMENT OF TRANSPORTATION PROJECT: HOOKSETT X-A000(407), 12537A COUNTIES AND CODES: MERRIMACK 013 DATE BIDS OPEN: OCTOBER 11, 2012 SCOPE OF WORK: ROADWAY IMPROVEMENTS LOCATION: US ROUTE 3/NH ROUTE 28 COMPLETION DATE: OCTOBER 17, 2014 A CONTINENTAL PAVING, INC. 1 CONTINENTAL DRIVE, LONDONDERRY, NH 03053 $ 4,074,351.95 B WEAVER BROS. CONST. CO., INC. PO BOX 1326, CONCORD, NH 03302 $ 4,277,634.05 C F.L. MERRILL CONSTRUCTION, INC. 619 SAND RD., PEMBROKE, NH 03275 $ 4,587,861.85 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 202.31 FILL ABANDONED PIPE CY 145. 150.00 21,750.00 160.00 23,200.00 148.00 21,460.00 202.35 HANDLING EXCAVATED CONTAMINATED SOILS CY 100. 30.00 3,000.00 20.00 2,000.00 20.45 2,045.00 202.41 REMOVAL OF EXISTING PIPE 0-24" DIAMETER LF 460. 10.00 4,600.00 7.50 3,450.00 9.50 4,370.00 202.42 REMOVAL OF EXISTING PIPE OVER 24" DIAMETER LF 175. 10.00 1,750.00 9.75 1,706.25 10.00 1,750.00 202.43 REMOVAL OF EXIST. ASBEST. CEMENT PIPE, 0-24" DIAM. LF 500. 65.00 32,500.00 21.00 10,500.00 18.90 9,450.00 202.5 REMOVAL OF CATCH BASINS, DROP INLETS, AND MANHOLES EA 12. 200.00 2,400.00 200.00 2,400.00 300.00 3,600.00 202.8 REMOVAL OF FENCE LF 925. 2.50 2,312.50 1.35 1,248.75 3.20 2,960.00 202.9 REMOVAL OF FUEL TANKS U 1. 10.00 10.00 1,100.00 1,100.00 1,100.00 1,100.00 203.1 COMMON EXCAVATION CY 25,700. 8.00 205,600.00 8.15 209,455.00 7.40 190,180.00 203.2 ROCK EXCAVATION CY 1,750. 25.00 43,750.00 35.00 61,250.00 102.00 178,500.00 203.6 EMBANKMENT-IN-PLACE (F) CY 660. 6.00 3,960.00 3.85 2,541.00 2.80 1,848.00 206.1 COMMON STRUCTURE EXCAVATION CY 95. 20.00 1,900.00 9.50 902.50 13.80 1,311.00 206.19 COMMON STRUCTURE EXCAVATION EXPLORATORY CY 100. 50.00 5,000.00 50.00 5,000.00 27.60 2,760.00 206.2 ROCK STRUCTURE EXCAVATION CY 1,348. 45.00 60,660.00 85.00 114,580.00 102.00 137,496.00 209.1 GRANULAR BACKFILL CY 355. 20.00 7,100.00 25.00 8,875.00 35.00 12,425.00 211.11 VIBRATION MONITORING SERVICES HR 35. 70.00 2,450.00 70.00 2,450.00 69.20 2,422.00 214. FINE GRADING U 1. 10,000.00 10,000.00 30,000.00 30,000.00 15,000.00 15,000.00 304.2 GRAVEL (F) CY 12,540. 18.00 225,720.00 13.35 167,409.00 15.50 194,370.00 304.301 CRUSHED GRAVEL CY 570. 20.00 11,400.00 19.00 10,830.00 20.00 11,400.00 304.35 CRUSHED GRAVEL FOR DRIVES CY 1,020. 20.00 20,400.00 25.65 26,163.00 22.10 22,542.00 304.399 TEMPORARY CRUSHED GRAVEL CY 1,375. 20.00 27,500.00 19.00 26,125.00 27.40 37,675.00 12537A PAGE 2 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 304.4 CRUSHED STONE (FINE GRADATION) (F) CY 3,370. 20.00 67,400.00 18.00 60,660.00 20.00 67,400.00 304.5 CRUSHED STONE (COARSE GRADATION) (F) CY 4,690. 20.00 93,800.00 18.00 84,420.00 20.00 93,800.00 403.11002 HOT BITUMINOUS PAVEMENT, MACHINE METHOD (QC/QA TIER 2) TON 7,425. 67.00 497,475.00 63.00 467,775.00 71.55 531,258.75 403.1109 HOT BITUMINOUS PAVEMENT, MACHINE METHOD, HIGH STRENGTH TON 2,200. 84.00 184,800.00 71.00 156,200.00 80.00 176,000.00 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON 635. 105.00 66,675.00 114.00 72,390.00 112.00 71,120.00 403.4 MATERIAL TRANSFER VEHICLE (MTV) TON 2,200. 1.00 2,200.00 1.00 2,200.00 1.06 2,332.00 403.6 PAVEMENT JOINT ADHESIVE LF 36,000. .35 12,600.00 .23 8,280.00 .25 9,000.00 403.99 TEMPORARY BITUMINOUS PAVEMENT TON 1,000. 90.00 90,000.00 112.00 112,000.00 103.50 103,500.00 417. COLD PLANING BITUMINOUS SURFACES SY 1,725. 5.00 8,625.00 5.10 8,797.50 5.30 9,142.50 504.1 COMMON BRIDGE EXCAVATION (F) CY 450. 15.00 6,750.00 10.00 4,500.00 9.70 4,365.00 508. STRUCTURAL FILL CY 50. 25.00 1,250.00 35.00 1,750.00 37.00 1,850.00 585.2 STONE FILL, CLASS B CY 10. 25.00 250.00 35.00 350.00 46.70 467.00 585.7 STONE FILL, CLASS G CY 50. 30.00 1,500.00 35.00 1,750.00 30.60 1,530.00 592.31 PRECAST CONCRETE MODULAR WALL SF 1,400. 34.00 47,600.00 52.00 72,800.00 35.00 49,000.00 593.411 GEOTEXTILE; PERM CONTROL CL.1, NON-WOVEN SY 260. 4.00 1,040.00 2.00 520.00 3.70 962.00 603.0001 VIDEO INSPECTION LF 5,005. .65 3,253.25 .70 3,503.50 1.06 5,305.30 603.00212 12" R.C. PIPE, 2000D LF 64. 40.00 2,560.00 50.00 3,200.00 42.00 2,688.00 603.00215 15" R.C. PIPE, 2000D LF 195. 45.00 8,775.00 52.00 10,140.00 45.60 8,892.00 603.00218 18" R.C. PIPE, 2000D LF 66. 50.00 3,300.00 60.00 3,960.00 52.80 3,484.80 603.00224 24" R.C. PIPE, 2000D LF 9. 100.00 900.00 180.00 1,620.00 117.00 1,053.00 603.34118 18" STEEL END SECTIONS EA 1. 200.00 200.00 145.00 145.00 153.40 153.40 603.81006 6" PVC PIPE LF 26. 25.00 650.00 40.00 1,040.00 38.90 1,011.40 603.82212 12" PE PIPE (TYPE S) LF 140. 35.00 4,900.00 32.00 4,480.00 33.40 4,676.00 603.82215 15" PE PIPE (TYPE S) LF 1,580. 36.00 56,880.00 34.00 53,720.00 36.40 57,512.00 603.82218 18" PE PIPE (TYPE S) LF 2,040. 40.00 81,600.00 37.00 75,480.00 41.00 83,640.00 603.82224 24" PE PIPE (TYPE S) LF 890. 45.00 40,050.00 52.00 46,280.00 55.00 48,950.00 604.0007 POLYETHYLENE LINER EA 90. 110.00 9,900.00 180.00 16,200.00 161.00 14,490.00 604.12 CATCH BASINS TYPE B U 91. 2,000.00 182,000.00 1,800.00 163,800.00 2,100.00 191,100.00 604.125 CATCH BASINS TYPE B, 5-FOOT DIAMETER U 4. 2,700.00 10,800.00 2,200.00 8,800.00 2,600.00 10,400.00 604.126 CATCH BASINS TYPE B, 6-FOOT DIAMETER U 2. 3,500.00 7,000.00 3,000.00 6,000.00 3,700.00 7,400.00 604.22 DROP INLETS TYPE B U 9. 1,800.00 16,200.00 1,800.00 16,200.00 1,970.00 17,730.00 604.324 DRAINAGE MANHOLES, 4-FOOT DIAMETER U 8. 2,000.00 16,000.00 2,000.00 16,000.00 2,640.00 21,120.00 604.4 RECONSTRUCTING/ADJUSTING CATCH BASIN & DROP INLET LF 12. 350.00 4,200.00 355.00 4,260.00 300.00 3,600.00 12537A PAGE 3 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 605.506 6" PERF. CORR. POLYETHYL PIPE UND. LF 2,600. 15.00 39,000.00 19.50 50,700.00 15.75 40,950.00 605.79 UNDERDRAIN FLUSHING BASINS EA 2. 500.00 1,000.00 450.00 900.00 376.00 752.00 606.417 PORTABLE CONCRETE BARRIER FOR TRAFFIC CONTROL LF 120. 20.00 2,400.00 12.00 1,440.00 32.70 3,924.00 606.6311 SAFETY RAIL, W/GUARD, STEEL LF 170. 95.00 16,150.00 100.00 17,000.00 118.00 20,060.00 607.67426 26' STEEL GATE WITH STOP POSTS, 42" HIGH U 1. 3,000.00 3,000.00 3,000.00 3,000.00 9,000.00 9,000.00 607.67430 30' STEEL GATE WITH STOP POSTS, 42" HIGH U 1. 3,000.00 3,000.00 3,000.00 3,000.00 9,200.00 9,200.00 607.98 RESETTING GATE U 1. 1,500.00 1,500.00 1,100.00 1,100.00 1,100.00 1,100.00 607.996 TEMPORARY CHAIN LINK FENCE, 6 FEET HIGH LF 1,100. 11.75 12,925.00 12.00 13,200.00 13.00 14,300.00 608.12 2" BITUMINOUS SIDEWALK (F) SY 975. 13.00 12,675.00 13.25 12,918.75 14.90 14,527.50 608.24 4" CONCRETE SIDEWALK (F) SY 65. 35.00 2,275.00 42.00 2,730.00 66.00 4,290.00 608.26 6" CONCRETE SIDEWALK (F) SY 106. 40.00 4,240.00 44.00 4,664.00 70.20 7,441.20 608.54 DETECTABLE WARNING DEVICES, CAST IRON SY 6. 350.00 2,100.00 360.00 2,160.00 436.00 2,616.00 609.01 STRAIGHT GRANITE CURB LF 3,310. 17.50 57,925.00 17.00 56,270.00 23.00 76,130.00 609.02 CURVED GRANITE CURB LF 525. 25.50 13,387.50 26.00 13,650.00 34.40 18,060.00 609.216 STRAIGHT GRANITE SLOPE CURB 6" HIGH LF 565. 16.00 9,040.00 16.00 9,040.00 21.40 12,091.00 609.226 STRAIGHT GRANITE SLOPE CURB WITH RADIAL JOINTS, 6" HIGH LF 80. 16.00 1,280.00 16.00 1,280.00 21.40 1,712.00 609.23 CURVED GRANITE SLOPE CURB LF 10. 67.00 670.00 67.00 670.00 76.00 760.00 609.5 RESET GRANITE CURB LF 2,700. 7.00 18,900.00 6.90 18,630.00 11.00 29,700.00 609.924 SPECIAL STRAIGHT GRANITE CURB (REVEAL UP TO 12") LF 870. 37.00 32,190.00 37.00 32,190.00 43.00 37,410.00 609.930 SPECIAL STRAIGHT GRANITE CURB (REVEAL 12" - 18") LF 630. 87.00 54,810.00 80.00 50,400.00 86.60 54,558.00 609.936 SPECIAL STRAIGHT GRANITE CURB (REVEAL 18" - 24") LF 35. 117.00 4,095.00 120.00 4,200.00 165.00 5,775.00 611.05204 4" CEMENT LINED DUCTILE IRON WATER PIPE, CL 52 LF 15. 65.00 975.00 60.00 900.00 60.00 900.00 611.05206 6" CEMENT LINED DUCTILE IRON WATER PIPE, CL 52 LF 310. 55.00 17,050.00 70.00 21,700.00 61.40 19,034.00 611.05208 8" CEMENT LINED DUCTILE IRON WATER PIPE, CL 52 LF 220. 60.00 13,200.00 75.00 16,500.00 90.00 19,800.00 611.05210 10" CEMENT LINED DUCTILE IRON WATER PIPE, CL 52 LF 15. 75.00 1,125.00 80.00 1,200.00 86.00 1,290.00 611.05212 12" CEMENT LINED DUCTILE IRON WATER PIPE, CL 52 LF 2,900. 75.00 217,500.00 80.00 232,000.00 79.00 229,100.00 611.41208 12" X 8" REDUCER EA 2. 500.00 1,000.00 500.00 1,000.00 640.00 1,280.00 611.41210 12" X 10" REDUCER EA 1. 500.00 500.00 525.00 525.00 650.00 650.00 611.50107 3/4" COPPER WATER PIPE LF 30. 30.00 900.00 36.00 1,080.00 29.50 885.00 12537A PAGE 4 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 611.5011 1" COPPER WATER PIPE LF 100. 35.00 3,500.00 36.00 3,600.00 31.00 3,100.00 611.50115 1 1/2" COPPER WATER PIPE LF 40. 40.00 1,600.00 44.00 1,760.00 35.60 1,424.00 611.51007 3/4" CORPORATION STOP EA 1. 250.00 250.00 250.00 250.00 500.00 500.00 611.5101 1" CORPORATION STOP EA 5. 250.00 1,250.00 300.00 1,500.00 520.00 2,600.00 611.51015 1 1/2" CORPORATION STOP EA 1. 300.00 300.00 575.00 575.00 620.00 620.00 611.70006 6" FITTING EA 7. 300.00 2,100.00 375.00 2,625.00 280.00 1,960.00 611.70008 8" FITTING EA 10. 300.00 3,000.00 475.00 4,750.00 345.00 3,450.00 611.70012 12" FITTING EA 50. 500.00 25,000.00 900.00 45,000.00 673.00 33,650.00 611.71208 8" INSERTION VALVE & SLEEVE EA 4. 6,500.00 26,000.00 5,200.00 20,800.00 6,300.00 25,200.00 611.71210 10" INSERTION VALVE & SLEEVE EA 1. 8,300.00 8,300.00 8,000.00 8,000.00 11,570.00 11,570.00 611.74 CHLORINE INJECTION TAP EA 15. 500.00 7,500.00 850.00 12,750.00 630.00 9,450.00 611.81 HYDRANTS EA 4. 3,000.00 12,000.00 4,200.00 16,800.00 4,000.00 16,000.00 611.811 ADJUSTING/RELOCATING HYDRANTS EA 1. 1,500.00 1,500.00 1,900.00 1,900.00 1,950.00 1,950.00 611.951 WATER MAIN INSULATION SY 90. 25.00 2,250.00 20.00 1,800.00 16.00 1,440.00 612.191 TEMPORARY SEWAGE HAULING U 1. 2,000.00 2,000.00 10,000.00 10,000.00 11,000.00 11,000.00 612.199 TEMPORARY BYPASS PUMPING U 1. 2,500.00 2,500.00 10,000.00 10,000.00 3,725.00 3,725.00 612.3104 SEWER MANHOLE, 4-FOOT DIAMETER VF 18. 350.00 6,300.00 465.00 8,370.00 290.00 5,220.00 612.42206 6" DUCTILE IRON SEWER FORCE MAIN, CL 52 LF 90. 70.00 6,300.00 85.00 7,650.00 90.00 8,100.00 612.52 SOFT START MOTOR U 2. 1,750.00 3,500.00 8,000.00 16,000.00 6,400.00 12,800.00 612.61506 6" PVC SEWER SERVICE, SDR-35 LF 15. 50.00 750.00 50.00 750.00 53.40 801.00 612.61512 12" PVC SEWER PIPE, SDR-35 LF 270. 40.00 10,800.00 65.00 17,550.00 67.50 18,225.00 614.511 CONCRETE PULL BOX 14" EA 25. 280.00 7,000.00 285.00 7,125.00 340.00 8,500.00 614.5183 30-INCH CONCRETE FIBER OPTIC MANHOLE EA 3. 1,800.00 5,400.00 1,835.00 5,505.00 2,490.00 7,470.00 614.523 MOLDED PULL BOX 17"X30" EA 5. 350.00 1,750.00 355.00 1,775.00 450.00 2,250.00 614.73114 3" PVC CONDUIT, SCHEDULE 40 LF 1,900. 6.00 11,400.00 6.10 11,590.00 7.00 13,300.00 614.73118 3" PVC CONDUIT, SCHEDULE 80 LF 1,050. 10.00 10,500.00 10.25 10,762.50 15.00 15,750.00 614.74221 4" 2-DUCT HDPE CONDUIT, SDR 13.5 LF 1,950. 17.00 33,150.00 17.40 33,930.00 17.80 34,710.00 615.02 TRAFFIC SIGN TYPE B (F) SF 74. 33.00 2,442.00 33.00 2,442.00 53.20 3,936.80 615.03 TRAFFIC SIGN TYPE C (F) SF 152. 38.00 5,776.00 40.00 6,080.00 42.60 6,475.20 615.06 TRAFFIC SIGN TYPE CC (F) SF 38.75 10.00 387.50 10.00 387.50 16.00 620.00 616.122 COMMUNICATIONS CABLE LF 1,050. 2.75 2,887.50 2.80 2,940.00 3.40 3,570.00 616.151 TRAFFIC SIGNAL (FIBER OPTIC) U 1. 11,000.00 11,000.00 11,200.00 11,200.00 12,240.00 12,240.00 616.161 TRAFFIC SIGNALS (TEMP.) U 1. 1,300.00 1,300.00 1,350.00 1,350.00 7,130.00 7,130.00 616.162 TRAFFIC SIGNALS (TEMP.) U 1. 8,000.00 8,000.00 8,200.00 8,200.00 13,300.00 13,300.00 616.163 TRAFFIC SIGNALS (TEMP.) U 1. 8,000.00 8,000.00 8,200.00 8,200.00 12,500.00 12,500.00 616.191 ALTERATIONS TO TRAFFIC SIGNALS U 1. 95,500.00 95,500.00 97,000.00 97,000.00 125,400.00 125,400.00 616.192 ALTERATIONS TO TRAFFIC SIGNALS U 1. 97,500.00 97,500.00 100,000.00 100,000.00 125,400.00 125,400.00 12537A PAGE 5 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 616.193 ALTERATIONS TO TRAFFIC SIGNALS U 1. 111,000.00 111,000.00 113,500.00 113,500.00 146,700.00 146,700.00 616.194 ALTERATIONS TO TRAFFIC SIGNALS U 1. 800.00 800.00 820.00 820.00 3,100.00 3,100.00 616.195 ALTERATIONS TO TRAFFIC SIGNALS U 1. 800.00 800.00 820.00 820.00 3,100.00 3,100.00 616.196 ALTERATIONS TO TRAFFIC SIGNALS U 1. 800.00 800.00 820.00 820.00 3,100.00 3,100.00 618.6 UNIFORMED OFFICERS $ 1. 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 618.61 UNIFORMED OFFICERS WITH VEHICLE $ 1. 50,000.00 50,000.00 50,000.00 50,000.00 50,000.00 50,000.00 618.7 FLAGGERS HR 6,800. 22.00 149,600.00 22.00 149,600.00 21.30 144,840.00 619.1 MAINTENANCE OF TRAFFIC U 1. 75,000.00 75,000.00 90,000.00 90,000.00 38,900.00 38,900.00 619.1009 DUST CONTROL U 1. 10,000.00 10,000.00 20,000.00 20,000.00 16,000.00 16,000.00 619.25 PORTABLE CHANGEABLE MESSAGE SIGN U 4. 4,000.00 16,000.00 5,400.00 21,600.00 2,700.00 10,800.00 621.61 FIBER OPTIC DELINEATOR EA 10. 100.00 1,000.00 105.00 1,050.00 145.00 1,450.00 622.2 CONCRETE BOUNDS EA 37. 385.00 14,245.00 395.00 14,615.00 400.00 14,800.00 625.2 CONCRETE LIGHT POLE BASES, TYPE B EA 22. 500.00 11,000.00 515.00 11,330.00 870.00 19,140.00 628.1 SAWED CONCRETE PAVEMENT LF 360. 2.00 720.00 3.50 1,260.00 1.30 468.00 628.2 SAWED BITUMINOUS PAVEMENT LF 4,225. 1.00 4,225.00 .95 4,013.75 1.30 5,492.50 632.0104 RETROREFLECTIVE PAINT PAVE. MARKING, 4" LINE LF 23,600. .14 3,304.00 .15 3,540.00 .07 1,652.00 632.0106 RETROREFLECTIVE PAINT PAVE. MARKING, 6" LINE LF 940. .19 178.60 .20 188.00 .10 94.00 632.0118 RETROREFLECTIVE PAINT PAVE. MARKING, 18" LINE LF 770. 1.25 962.50 1.28 985.60 1.00 770.00 632.3106 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 6" LINE LF 480. .62 297.60 .65 312.00 1.25 600.00 632.3118 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 18" LINE LF 385. 2.45 943.25 2.50 962.50 3.70 1,424.50 632.32 RETROREFLECT. THERMOPLAS. PAVEMENT MARKING, SYMBOL OR WORD SF 925. 4.65 4,301.25 4.75 4,393.75 10.40 9,620.00 632.911 OBLITERATE PAVE. MARKING LINE, 12" WIDE & UNDER LF 18,200. .31 5,642.00 .32 5,824.00 .85 15,470.00 632.912 OBLITERATE PAVE. MARKING LINE, OVER 12" WIDE LF 240. .95 228.00 .96 230.40 1.00 240.00 632.92 OBLITERATE PAVEMENT MARKING, SYMBOL OR WORD SF 730. .95 693.50 .96 700.80 1.00 730.00 641. LOAM CY 200. 20.00 4,000.00 20.00 4,000.00 27.00 5,400.00 645.154 BARK MULCH 4 INCHES DEEP SY 200. 5.50 1,100.00 9.50 1,900.00 10.00 2,000.00 645.3 EROSION STONE TON 500. 18.00 9,000.00 20.00 10,000.00 18.75 9,375.00 645.41 TEMPORARY SLOPE STABILIZATION TYPE A SY 780. 1.50 1,170.00 1.38 1,076.40 1.60 1,248.00 645.43 TEMPORARY SLOPE STABILIZATION TYPE C SY 370. 2.00 740.00 1.48 547.60 1.60 592.00 645.531 SILT FENCE LF 2,750. 3.00 8,250.00 1.50 4,125.00 2.50 6,875.00 645.7 STORM WATER POLLUTION PREVENTION PLAN U 1. 3,250.00 3,250.00 2,300.00 2,300.00 3,500.00 3,500.00 12537A PAGE 6 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 645.71 MONITORING SWPPP AND EROSION AND SEDIMENT CONTROLS HR 300. 50.00 15,000.00 44.00 13,200.00 53.00 15,900.00 646.31 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS SY 5,400. .50 2,700.00 .37 1,998.00 .55 2,970.00 659.5 IRRIGATION SYSTEM U 1. 10,000.00 10,000.00 24,000.00 24,000.00 16,000.00 16,000.00 670.066 MAILBOX SUPPORT ASSEMBLIES EA 1. 400.00 400.00 150.00 150.00 161.00 161.00 670.1508 RELOCATE ELECTRIC AND TELEPHONE SERVICE U 1. 15,000.00 15,000.00 16,000.00 16,000.00 22,820.00 22,820.00 670.443 INSTALL NATURAL GAS SERVICE U 1. 3,500.00 3,500.00 5,000.00 5,000.00 21,200.00 21,200.00 677.51072 72-STRAND SINGLE MODE FIBER OPTIC CABLE LF 2,000. 10.00 20,000.00 10.00 20,000.00 5.75 11,500.00 692. MOBILIZATION U 1. 85,000.00 85,000.00 185,000.00 185,000.00 103,000.00 103,000.00 693. ON-THE-JOB TRAINING OF UNSKILLED WORKERS $ 1. 600.00 600.00 600.00 600.00 600.00 600.00 697.21 PROJECT HEALTH AND SAFETY PLAN U 1. 3,000.00 3,000.00 3,000.00 3,000.00 3,200.00 3,200.00 697.41 CRITICAL PATH METHOD (CPM) ELECTRONIC SCHEDULE U 1. 5,000.00 5,000.00 10,000.00 10,000.00 3,200.00 3,200.00 698.12 FIELD OFFICE TYPE B MON 25. 2,000.00 50,000.00 1,500.00 37,500.00 1,500.00 37,500.00 698.2 PHYSICAL TESTING LABORATORY MON 16. 1,500.00 24,000.00 800.00 12,800.00 1,100.00 17,600.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 25,000.00 25,000.00 25,000.00 25,000.00 25,000.00 25,000.00 1008.4 ALTERATIONS AND ADDITIONS AS NEEDED - UTILITY ADJUSTMENTS $ 1. 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 1009.21 TREATMENT OR DISPOSAL OF CONTAMINATED GROUNDWATER (FRAC TANK) $ 1. 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 1010.15 FUEL ADJUSTMENT $ 1. 40,000.00 40,000.00 40,000.00 40,000.00 40,000.00 40,000.00 1010.2 ASPHALT CEMENT ADJUSTMENT $ 1. 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 1010.3 QUALITY CONTROL QUALITY ASSURANCE (QC/QA ASPHALT $ 1. 25,000.00 25,000.00 25,000.00 25,000.00 25,000.00 25,000.00 $4,074,351.95 $4,277,634.05 $4,587,861.85 STATE OF NEW HAMPSHIRE DEPARTMENT OF TRANSPORTATION A-PS&E COMPARISION PROJECT: HOOKSETT X-A000(407), 12537A COUNTIES AND CODES: MERRIMACK 013 DATE BIDS OPEN: OCTOBER 11, 2012 SCOPE OF WORK: ROADWAY IMPROVEMENTS LOCATION: US ROUTE 3/NH ROUTE 28 COMPLETION DATE: OCTOBER 17, 2014 A CONTINENTAL PAVING, INC. 1 CONTINENTAL DRIVE, LONDONDERRY, NH 03053 $ 4,074,351.95 B WEAVER BROS. CONST. CO., INC. PO BOX 1326, CONCORD, NH 03302 $ 4,277,634.05 C F.L. MERRILL CONSTRUCTION, INC. 619 SAND RD., PEMBROKE, NH 03275 $ 4,587,861.85 A-BIDDER PS&E ----------------------- ----------------------- A-PS&E ITEM NO. ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT DIFFERENCE 202.31 FILL ABANDONED PIPE CY 145. 150.00 21,750.00 200.00 29,000.00 -7,250.00 202.35 HANDLING EXCAVATED CONTAMINATED SOILS CY 100. 30.00 3,000.00 15.00 1,500.00 1,500.00 202.41 REMOVAL OF EXISTING PIPE 0-24" DIAMETER LF 460. 10.00 4,600.00 10.00 4,600.00 202.42 REMOVAL OF EXISTING PIPE OVER 24" DIAMETER LF 175. 10.00 1,750.00 15.00 2,625.00 -875.00 202.43 REMOVAL OF EXIST. ASBEST. CEMENT PIPE, 0-24" DIAM. LF 500. 65.00 32,500.00 30.00 15,000.00 17,500.00 202.5 REMOVAL OF CATCH BASINS, DROP INLETS, AND MANHOLES EA 12. 200.00 2,400.00 250.00 3,000.00 -600.00 202.8 REMOVAL OF FENCE LF 925. 2.50 2,312.50 2.00 1,850.00 462.50 202.9 REMOVAL OF FUEL TANKS U 1. 10.00 10.00 1,000.00 1,000.00 -990.00 203.1 COMMON EXCAVATION CY 25,700. 8.00 205,600.00 6.00 154,200.00 51,400.00 203.2 ROCK EXCAVATION CY 1,750. 25.00 43,750.00 20.00 35,000.00 8,750.00 203.6 EMBANKMENT-IN-PLACE (F) CY 660. 6.00 3,960.00 5.00 3,300.00 660.00 206.1 COMMON STRUCTURE EXCAVATION CY 95. 20.00 1,900.00 15.00 1,425.00 475.00 206.19 COMMON STRUCTURE EXCAVATION EXPLORATORY CY 100. 50.00 5,000.00 50.00 5,000.00 206.2 ROCK STRUCTURE EXCAVATION CY 1,348. 45.00 60,660.00 30.00 40,440.00 20,220.00 209.1 GRANULAR BACKFILL CY 355. 20.00 7,100.00 25.00 8,875.00 -1,775.00 211.11 VIBRATION MONITORING SERVICES HR 35. 70.00 2,450.00 60.00 2,100.00 350.00 214. FINE GRADING U 1. 10,000.00 10,000.00 75,000.00 75,000.00 -65,000.00 304.2 GRAVEL (F) CY 12,540. 18.00 225,720.00 15.00 188,100.00 37,620.00 304.301 CRUSHED GRAVEL CY 570. 20.00 11,400.00 18.00 10,260.00 1,140.00 304.35 CRUSHED GRAVEL FOR DRIVES CY 1,020. 20.00 20,400.00 22.00 22,440.00 -2,040.00 12537A PAGE 2 A-BIDDER PS&E ----------------------- ----------------------- A-PS&E ITEM NO. ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT DIFFERENCE 304.399 TEMPORARY CRUSHED GRAVEL CY 1,375. 20.00 27,500.00 25.00 34,375.00 -6,875.00 304.4 CRUSHED STONE (FINE GRADATION) (F) CY 3,370. 20.00 67,400.00 18.00 60,660.00 6,740.00 304.5 CRUSHED STONE (COARSE GRADATION) (F) CY 4,690. 20.00 93,800.00 18.00 84,420.00 9,380.00 403.11002 HOT BITUMINOUS PAVEMENT, MACHINE METHOD (QC/QA TIER 2) TON 7,425. 67.00 497,475.00 68.00 504,900.00 -7,425.00 403.1109 HOT BITUMINOUS PAVEMENT, MACHINE METHOD, HIGH STRENGTH TON 2,200. 84.00 184,800.00 75.00 165,000.00 19,800.00 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON 635. 105.00 66,675.00 90.00 57,150.00 9,525.00 403.4 MATERIAL TRANSFER VEHICLE (MTV) TON 2,200. 1.00 2,200.00 1.00 2,200.00 403.6 PAVEMENT JOINT ADHESIVE LF 36,000. .35 12,600.00 .25 9,000.00 3,600.00 403.99 TEMPORARY BITUMINOUS PAVEMENT TON 1,000. 90.00 90,000.00 75.00 75,000.00 15,000.00 417. COLD PLANING BITUMINOUS SURFACES SY 1,725. 5.00 8,625.00 5.00 8,625.00 504.1 COMMON BRIDGE EXCAVATION (F) CY 450. 15.00 6,750.00 20.00 9,000.00 -2,250.00 508. STRUCTURAL FILL CY 50. 25.00 1,250.00 30.00 1,500.00 -250.00 585.2 STONE FILL, CLASS B CY 10. 25.00 250.00 50.00 500.00 -250.00 585.7 STONE FILL, CLASS G CY 50. 30.00 1,500.00 30.00 1,500.00 592.31 PRECAST CONCRETE MODULAR WALL SF 1,400. 34.00 47,600.00 40.00 56,000.00 -8,400.00 593.411 GEOTEXTILE; PERM CONTROL CL.1, NON-WOVEN SY 260. 4.00 1,040.00 3.00 780.00 260.00 603.0001 VIDEO INSPECTION LF 5,005. .65 3,253.25 1.00 5,005.00 -1,751.75 603.00212 12" R.C. PIPE, 2000D LF 64. 40.00 2,560.00 50.00 3,200.00 -640.00 603.00215 15" R.C. PIPE, 2000D LF 195. 45.00 8,775.00 35.00 6,825.00 1,950.00 603.00218 18" R.C. PIPE, 2000D LF 66. 50.00 3,300.00 40.00 2,640.00 660.00 603.00224 24" R.C. PIPE, 2000D LF 9. 100.00 900.00 60.00 540.00 360.00 603.34118 18" STEEL END SECTIONS EA 1. 200.00 200.00 250.00 250.00 -50.00 603.81006 6" PVC PIPE LF 26. 25.00 650.00 15.00 390.00 260.00 603.82212 12" PE PIPE (TYPE S) LF 140. 35.00 4,900.00 27.00 3,780.00 1,120.00 603.82215 15" PE PIPE (TYPE S) LF 1,580. 36.00 56,880.00 31.00 48,980.00 7,900.00 603.82218 18" PE PIPE (TYPE S) LF 2,040. 40.00 81,600.00 36.00 73,440.00 8,160.00 603.82224 24" PE PIPE (TYPE S) LF 890. 45.00 40,050.00 42.00 37,380.00 2,670.00 604.0007 POLYETHYLENE LINER EA 90. 110.00 9,900.00 150.00 13,500.00 -3,600.00 604.12 CATCH BASINS TYPE B U 91. 2,000.00 182,000.00 1,800.00 163,800.00 18,200.00 604.125 CATCH BASINS TYPE B, 5-FOOT DIAMETER U 4. 2,700.00 10,800.00 3,000.00 12,000.00 -1,200.00 604.126 CATCH BASINS TYPE B, 6-FOOT DIAMETER U 2. 3,500.00 7,000.00 3,525.00 7,050.00 -50.00 604.22 DROP INLETS TYPE B U 9. 1,800.00 16,200.00 1,450.00 13,050.00 3,150.00 604.324 DRAINAGE MANHOLES, 4-FOOT DIAMETER U 8. 2,000.00 16,000.00 1,850.00 14,800.00 1,200.00 604.4 RECONSTRUCTING/ADJUSTING CATCH BASIN & DROP INLET LF 12. 350.00 4,200.00 350.00 4,200.00 605.506 6" PERF. CORR. POLYETHYL PIPE UND. LF 2,600. 15.00 39,000.00 15.00 39,000.00 12537A PAGE 3 A-BIDDER PS&E ----------------------- ----------------------- A-PS&E ITEM NO. ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT DIFFERENCE 605.79 UNDERDRAIN FLUSHING BASINS EA 2. 500.00 1,000.00 400.00 800.00 200.00 606.417 PORTABLE CONCRETE BARRIER FOR TRAFFIC CONTROL LF 120. 20.00 2,400.00 25.00 3,000.00 -600.00 606.6311 SAFETY RAIL, W/GUARD, STEEL LF 170. 95.00 16,150.00 50.00 8,500.00 7,650.00 607.67426 26' STEEL GATE WITH STOP POSTS, 42" HIGH U 1. 3,000.00 3,000.00 3,500.00 3,500.00 -500.00 607.67430 30' STEEL GATE WITH STOP POSTS, 42" HIGH U 1. 3,000.00 3,000.00 3,500.00 3,500.00 -500.00 607.98 RESETTING GATE U 1. 1,500.00 1,500.00 1,000.00 1,000.00 500.00 607.996 TEMPORARY CHAIN LINK FENCE, 6 FEET HIGH LF 1,100. 11.75 12,925.00 7.00 7,700.00 5,225.00 608.12 2" BITUMINOUS SIDEWALK (F) SY 975. 13.00 12,675.00 12.00 11,700.00 975.00 608.24 4" CONCRETE SIDEWALK (F) SY 65. 35.00 2,275.00 35.00 2,275.00 608.26 6" CONCRETE SIDEWALK (F) SY 106. 40.00 4,240.00 40.00 4,240.00 608.54 DETECTABLE WARNING DEVICES, CAST IRON SY 6. 350.00 2,100.00 310.00 1,860.00 240.00 609.01 STRAIGHT GRANITE CURB LF 3,310. 17.50 57,925.00 15.00 49,650.00 8,275.00 609.02 CURVED GRANITE CURB LF 525. 25.50 13,387.50 25.00 13,125.00 262.50 609.216 STRAIGHT GRANITE SLOPE CURB 6" HIGH LF 565. 16.00 9,040.00 13.00 7,345.00 1,695.00 609.226 STRAIGHT GRANITE SLOPE CURB WITH RADIAL JOINTS, 6" HIGH LF 80. 16.00 1,280.00 14.00 1,120.00 160.00 609.23 CURVED GRANITE SLOPE CURB LF 10. 67.00 670.00 50.00 500.00 170.00 609.5 RESET GRANITE CURB LF 2,700. 7.00 18,900.00 7.50 20,250.00 -1,350.00 609.924 SPECIAL STRAIGHT GRANITE CURB (REVEAL UP TO 12") LF 870. 37.00 32,190.00 25.00 21,750.00 10,440.00 609.930 SPECIAL STRAIGHT GRANITE CURB (REVEAL 12" - 18") LF 630. 87.00 54,810.00 60.00 37,800.00 17,010.00 609.936 SPECIAL STRAIGHT GRANITE CURB (REVEAL 18" - 24") LF 35. 117.00 4,095.00 75.00 2,625.00 1,470.00 611.05204 4" CEMENT LINED DUCTILE IRON WATER PIPE, CL 52 LF 15. 65.00 975.00 50.00 750.00 225.00 611.05206 6" CEMENT LINED DUCTILE IRON WATER PIPE, CL 52 LF 310. 55.00 17,050.00 60.00 18,600.00 -1,550.00 611.05208 8" CEMENT LINED DUCTILE IRON WATER PIPE, CL 52 LF 220. 60.00 13,200.00 70.00 15,400.00 -2,200.00 611.05210 10" CEMENT LINED DUCTILE IRON WATER PIPE, CL 52 LF 15. 75.00 1,125.00 80.00 1,200.00 -75.00 611.05212 12" CEMENT LINED DUCTILE IRON WATER PIPE, CL 52 LF 2,900. 75.00 217,500.00 90.00 261,000.00 -43,500.00 611.41208 12" X 8" REDUCER EA 2. 500.00 1,000.00 800.00 1,600.00 -600.00 611.41210 12" X 10" REDUCER EA 1. 500.00 500.00 1,000.00 1,000.00 -500.00 611.50107 3/4" COPPER WATER PIPE LF 30. 30.00 900.00 35.00 1,050.00 -150.00 611.5011 1" COPPER WATER PIPE LF 100. 35.00 3,500.00 40.00 4,000.00 -500.00 611.50115 1 1/2" COPPER WATER PIPE LF 40. 40.00 1,600.00 45.00 1,800.00 -200.00 611.51007 3/4" CORPORATION STOP EA 1. 250.00 250.00 175.00 175.00 75.00 611.5101 1" CORPORATION STOP EA 5. 250.00 1,250.00 220.00 1,100.00 150.00 12537A PAGE 4 A-BIDDER PS&E ----------------------- ----------------------- A-PS&E ITEM NO. ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT DIFFERENCE 611.51015 1 1/2" CORPORATION STOP EA 1. 300.00 300.00 300.00 300.00 611.70006 6" FITTING EA 7. 300.00 2,100.00 500.00 3,500.00 -1,400.00 611.70008 8" FITTING EA 10. 300.00 3,000.00 600.00 6,000.00 -3,000.00 611.70012 12" FITTING EA 50. 500.00 25,000.00 800.00 40,000.00 -15,000.00 611.71208 8" INSERTION VALVE & SLEEVE EA 4. 6,500.00 26,000.00 5,000.00 20,000.00 6,000.00 611.71210 10" INSERTION VALVE & SLEEVE EA 1. 8,300.00 8,300.00 6,000.00 6,000.00 2,300.00 611.74 CHLORINE INJECTION TAP EA 15. 500.00 7,500.00 700.00 10,500.00 -3,000.00 611.81 HYDRANTS EA 4. 3,000.00 12,000.00 4,000.00 16,000.00 -4,000.00 611.811 ADJUSTING/RELOCATING HYDRANTS EA 1. 1,500.00 1,500.00 1,500.00 1,500.00 611.951 WATER MAIN INSULATION SY 90. 25.00 2,250.00 15.00 1,350.00 900.00 612.191 TEMPORARY SEWAGE HAULING U 1. 2,000.00 2,000.00 2,000.00 2,000.00 612.199 TEMPORARY BYPASS PUMPING U 1. 2,500.00 2,500.00 2,000.00 2,000.00 500.00 612.3104 SEWER MANHOLE, 4-FOOT DIAMETER VF 18. 350.00 6,300.00 280.00 5,040.00 1,260.00 612.42206 6" DUCTILE IRON SEWER FORCE MAIN, CL 52 LF 90. 70.00 6,300.00 40.00 3,600.00 2,700.00 612.52 SOFT START MOTOR U 2. 1,750.00 3,500.00 8,000.00 16,000.00 -12,500.00 612.61506 6" PVC SEWER SERVICE, SDR-35 LF 15. 50.00 750.00 60.00 900.00 -150.00 612.61512 12" PVC SEWER PIPE, SDR-35 LF 270. 40.00 10,800.00 120.00 32,400.00 -21,600.00 614.511 CONCRETE PULL BOX 14" EA 25. 280.00 7,000.00 280.00 7,000.00 614.5183 30-INCH CONCRETE FIBER OPTIC MANHOLE EA 3. 1,800.00 5,400.00 1,400.00 4,200.00 1,200.00 614.523 MOLDED PULL BOX 17"X30" EA 5. 350.00 1,750.00 350.00 1,750.00 614.73114 3" PVC CONDUIT, SCHEDULE 40 LF 1,900. 6.00 11,400.00 8.00 15,200.00 -3,800.00 614.73118 3" PVC CONDUIT, SCHEDULE 80 LF 1,050. 10.00 10,500.00 20.00 21,000.00 -10,500.00 614.74221 4" 2-DUCT HDPE CONDUIT, SDR 13.5 LF 1,950. 17.00 33,150.00 22.00 42,900.00 -9,750.00 615.02 TRAFFIC SIGN TYPE B (F) SF 74. 33.00 2,442.00 25.00 1,850.00 592.00 615.03 TRAFFIC SIGN TYPE C (F) SF 152. 38.00 5,776.00 25.25 3,838.00 1,938.00 615.06 TRAFFIC SIGN TYPE CC (F) SF 38.75 10.00 387.50 10.00 387.50 616.122 COMMUNICATIONS CABLE LF 1,050. 2.75 2,887.50 2.45 2,572.50 315.00 616.151 TRAFFIC SIGNAL (FIBER OPTIC) U 1. 11,000.00 11,000.00 26,500.00 26,500.00 -15,500.00 616.161 TRAFFIC SIGNALS (TEMP.) U 1. 1,300.00 1,300.00 3,000.00 3,000.00 -1,700.00 616.162 TRAFFIC SIGNALS (TEMP.) U 1. 8,000.00 8,000.00 12,000.00 12,000.00 -4,000.00 616.163 TRAFFIC SIGNALS (TEMP.) U 1. 8,000.00 8,000.00 10,000.00 10,000.00 -2,000.00 616.191 ALTERATIONS TO TRAFFIC SIGNALS U 1. 95,500.00 95,500.00 97,398.00 97,398.00 -1,898.00 616.192 ALTERATIONS TO TRAFFIC SIGNALS U 1. 97,500.00 97,500.00 100,911.00 100,911.00 -3,411.00 616.193 ALTERATIONS TO TRAFFIC SIGNALS U 1. 111,000.00 111,000.00 105,376.00 105,376.00 5,624.00 616.194 ALTERATIONS TO TRAFFIC SIGNALS U 1. 800.00 800.00 500.00 500.00 300.00 616.195 ALTERATIONS TO TRAFFIC SIGNALS U 1. 800.00 800.00 500.00 500.00 300.00 12537A PAGE 5 A-BIDDER PS&E ----------------------- ----------------------- A-PS&E ITEM NO. ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT DIFFERENCE 616.196 ALTERATIONS TO TRAFFIC SIGNALS U 1. 800.00 800.00 500.00 500.00 300.00 618.6 UNIFORMED OFFICERS $ 1. 20,000.00 20,000.00 20,000.00 20,000.00 618.61 UNIFORMED OFFICERS WITH VEHICLE $ 1. 50,000.00 50,000.00 50,000.00 50,000.00 618.7 FLAGGERS HR 6,800. 22.00 149,600.00 20.00 136,000.00 13,600.00 619.1 MAINTENANCE OF TRAFFIC U 1. 75,000.00 75,000.00 125,000.00 125,000.00 -50,000.00 619.1009 DUST CONTROL U 1. 10,000.00 10,000.00 36,000.00 36,000.00 -26,000.00 619.25 PORTABLE CHANGEABLE MESSAGE SIGN U 4. 4,000.00 16,000.00 3,500.00 14,000.00 2,000.00 621.61 FIBER OPTIC DELINEATOR EA 10. 100.00 1,000.00 50.00 500.00 500.00 622.2 CONCRETE BOUNDS EA 37. 385.00 14,245.00 275.00 10,175.00 4,070.00 625.2 CONCRETE LIGHT POLE BASES, TYPE B EA 22. 500.00 11,000.00 500.00 11,000.00 628.1 SAWED CONCRETE PAVEMENT LF 360. 2.00 720.00 3.00 1,080.00 -360.00 628.2 SAWED BITUMINOUS PAVEMENT LF 4,225. 1.00 4,225.00 1.25 5,281.25 -1,056.25 632.0104 RETROREFLECTIVE PAINT PAVE. MARKING, 4" LINE LF 23,600. .14 3,304.00 .15 3,540.00 -236.00 632.0106 RETROREFLECTIVE PAINT PAVE. MARKING, 6" LINE LF 940. .19 178.60 .75 705.00 -526.40 632.0118 RETROREFLECTIVE PAINT PAVE. MARKING, 18" LINE LF 770. 1.25 962.50 1.00 770.00 192.50 632.3106 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 6" LINE LF 480. .62 297.60 1.25 600.00 -302.40 632.3118 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 18" LINE LF 385. 2.45 943.25 4.00 1,540.00 -596.75 632.32 RETROREFLECT. THERMOPLAS. PAVEMENT MARKING, SYMBOL OR WORD SF 925. 4.65 4,301.25 5.00 4,625.00 -323.75 632.911 OBLITERATE PAVE. MARKING LINE, 12" WIDE & UNDER LF 18,200. .31 5,642.00 .30 5,460.00 182.00 632.912 OBLITERATE PAVE. MARKING LINE, OVER 12" WIDE LF 240. .95 228.00 1.00 240.00 -12.00 632.92 OBLITERATE PAVEMENT MARKING, SYMBOL OR WORD SF 730. .95 693.50 1.25 912.50 -219.00 641. LOAM CY 200. 20.00 4,000.00 20.00 4,000.00 645.154 BARK MULCH 4 INCHES DEEP SY 200. 5.50 1,100.00 5.00 1,000.00 100.00 645.3 EROSION STONE TON 500. 18.00 9,000.00 25.00 12,500.00 -3,500.00 645.41 TEMPORARY SLOPE STABILIZATION TYPE A SY 780. 1.50 1,170.00 1.50 1,170.00 645.43 TEMPORARY SLOPE STABILIZATION TYPE C SY 370. 2.00 740.00 2.00 740.00 645.531 SILT FENCE LF 2,750. 3.00 8,250.00 3.00 8,250.00 645.7 STORM WATER POLLUTION PREVENTION PLAN U 1. 3,250.00 3,250.00 3,000.00 3,000.00 250.00 645.71 MONITORING SWPPP AND EROSION AND SEDIMENT CONTROLS HR 300. 50.00 15,000.00 50.00 15,000.00 646.31 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS SY 5,400. .50 2,700.00 .75 4,050.00 -1,350.00 659.5 IRRIGATION SYSTEM U 1. 10,000.00 10,000.00 10,000.00 10,000.00 670.066 MAILBOX SUPPORT ASSEMBLIES EA 1. 400.00 400.00 200.00 200.00 200.00 12537A PAGE 6 A-BIDDER PS&E ----------------------- ----------------------- A-PS&E ITEM NO. ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT DIFFERENCE 670.1508 RELOCATE ELECTRIC AND TELEPHONE SERVICE U 1. 15,000.00 15,000.00 12,000.00 12,000.00 3,000.00 670.443 INSTALL NATURAL GAS SERVICE U 1. 3,500.00 3,500.00 6,000.00 6,000.00 -2,500.00 677.51072 72-STRAND SINGLE MODE FIBER OPTIC CABLE LF 2,000. 10.00 20,000.00 4.00 8,000.00 12,000.00 692. MOBILIZATION U 1. 85,000.00 85,000.00 204,400.00 204,400.00 -119,400.00 693. ON-THE-JOB TRAINING OF UNSKILLED WORKERS $ 1. 600.00 600.00 600.00 600.00 697.21 PROJECT HEALTH AND SAFETY PLAN U 1. 3,000.00 3,000.00 2,000.00 2,000.00 1,000.00 697.41 CRITICAL PATH METHOD (CPM) ELECTRONIC SCHEDULE U 1. 5,000.00 5,000.00 15,000.00 15,000.00 -10,000.00 698.12 FIELD OFFICE TYPE B MON 25. 2,000.00 50,000.00 1,500.00 37,500.00 12,500.00 698.2 PHYSICAL TESTING LABORATORY MON 16. 1,500.00 24,000.00 850.00 13,600.00 10,400.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 25,000.00 25,000.00 25,000.00 25,000.00 1008.4 ALTERATIONS AND ADDITIONS AS NEEDED - UTILITY ADJUSTMENTS $ 1. 20,000.00 20,000.00 20,000.00 20,000.00 1009.21 TREATMENT OR DISPOSAL OF CONTAMINATED GROUNDWATER (FRAC TANK) $ 1. 2,500.00 2,500.00 2,500.00 2,500.00 1010.15 FUEL ADJUSTMENT $ 1. 40,000.00 40,000.00 40,000.00 40,000.00 1010.2 ASPHALT CEMENT ADJUSTMENT $ 1. 20,000.00 20,000.00 20,000.00 20,000.00 1010.3 QUALITY CONTROL QUALITY ASSURANCE (QC/QA ASPHALT $ 1. 25,000.00 25,000.00 25,000.00 25,000.00 $4,074,351.95 $4,178,481.75 -104,129.80